Fresh water operation
A solenoid valve must be provided by the customer on site for the fresh water supply line. If the
AHU is equipped with an EUROCLIMA control, the necessary power supply is stipulated on the
wiring diagram.
Circulation water operation
A solenoid valve must be provided by the customer on site for the fresh water supply line and for
emptying. If the AHU is equipped with an EUROCLIMA control, the necessary power supply for the
valves is stipulated on the wiring diagram.
-
AHUs equipped from EUROCLIMA with control
If EUROCLIMA control system is included in the scope of supply and the evaporative humidifier
is in a circulation water operation, all components listed in
case all those components are controlled by the EUROCLIMA control system, mounted in the
piping system and where possible connected electronically, or supplied loose and prepared for
electrical connection.
-
AHUs equipped from EUROCLIMA without control
Required components listed in
osition 6 “Blowdown by tacosetter”
which
is always included in the scope of supply from EUROCLIMA) can be selected or must be pro-
vided on site, which is therefore the responsibility of the customer. All electrical components
must be integrated into the customers control system.
Figure 173:
Components of an evaporative humidifier system with circulation water operation
High pressure spray humidifier
The manufacturer of the high pressure spray humidifier must be contacted for support on the in-
stallation process.
Steam humidifier
The instructions of the manufacturer of the steam humidifier must be followed for the installation
process. For example, for the correct installation of the steam hose or for the connection of the
condensate drainage.
6.3 Drain for condensate and excess water
Each drain must be equipped with a siphon. Siphons are available as accessories from EURO-
CLIMA.
1
2
3
4
5
6
1 Fresh water solenoid valve
2 Drainage solenoid valve
3 Blowdown solenoid valve
4 Conductivity sensor
5 Level switch (max/min)
6 Blowdown by tacosetter
(water
amount of the drainage can be
set manually)
Содержание ZHK