Etrel INCH DUO Скачать руководство пользователя страница 9

 

  7    |   10 

 

Preparation for the Installation 

Once  the  foundation  is  dry  and  the  power  cables  are 

introduced  into  the  installation  pipe,  the  installation  of 

the charging station can begin. 

 

Clean  the  foundation,  its  surroundings  and  anchor 
bolts. 

 

Cut  the  installation  pipe  containing  the  power 
cables. 

 

Shorten the earthing strip

 

to the appropriate length 

and drill a hole in it. 
 

4-a 

 

 

 

 

4-b 

Preparation of Supply Cables 

Shorten the  power  cord and  remove  the  cable  sheath  - 

make sure there is no  voltage in it beforehand. Shorten 

the cables to the appropriate length (40 cm) so that you 

can  connect  them  to  the  terminals  in  the  charging 

station. 
Remove  20  mm  of  insulation from  all  cables  and attach 

and compress the appropriate crimp tubes on all cables. 

To  prevent  cables  from  getting  in  the  way  of  mounting 

the charging station, twist them into an installation pipe. 

Length of cables on the other side of the gland should be: 

 

Power supply cables (L1, L2, L3, N): 15 cm with 
insulation and stripped cable  2 cm without 
insulation 

 

Grounding cable: 10 cm with insulation 

 

Ethernet UTP cable: 17 cm with insulation 
 

 

Mounting the Charging Station 

Grab the charging station for both sockets, tilt it towards 

you and lift  it  slightly.  Place  the  charging  station on the 

foundation. In the event of strong winds, make sure that 

the charging station does not tip over. 

 

Unlock and open the door with the key located in one of 

the  sockets.  Take  the  five  nuts  and  tighten  them  firmly 

on the anchor bolts. 

 

Содержание INCH DUO

Страница 1: ...Ver 2021 3 EN Etrel INCH DUO QUICK START GUIDE EN...

Страница 2: ......

Страница 3: ...ersions of international standards The charging station is compliant with IEC 61851 Part 1 Part 21 2 Part 22 international standard which defines conductive AC electric vehicle charging and supports M...

Страница 4: ...trical codes legislation and ordinances Warning Before installing and wiring the charging station make sure that the power supply is disconnected remove fuses or deactivate the circuit breaker to prot...

Страница 5: ...ible that not all modules are part of an actual device LTE module Frequency bands LTE FDD B1 2100 MHz B3 1800 MHz B5 850 MHz B7 2600 MHz B8 900 MHz B20 800 MHz LTE TDD B38 2600 MHz B40 2300 MHz B41 25...

Страница 6: ...lass 2 appliance and must be protected with an upstream overvoltage protection Overcurrent protection Should be installed upstream to protect power supply cable and the charging device Differential pr...

Страница 7: ...g steel to the concrete foundation to enable construction of a larger foundation 1 b The foundation anchor must be assembled before installation Tighten the two nuts to each end of each rod 6 times In...

Страница 8: ...addition it needs to be temporarily clogged with paper or similar material at both ends so that the concrete cannot enter the pipe 4 When pouring concrete it is first poured into the vicinity of the...

Страница 9: ...20 mm of insulation from all cables and attach and compress the appropriate crimp tubes on all cables To prevent cables from getting in the way of mounting the charging station twist them into an ins...

Страница 10: ...rt all three phase conductors and the neutral N conductor into the circuit breaker terminals and tighten them firmly Attach the supply ground PE cable to the earthing clamp 8 b When charging station i...

Страница 11: ...g station may affect the measurement results or be damaged if tested with higher voltage Before closing the station check the condition of the over current protection elements and the residual current...

Страница 12: ...te or for troubleshooting please look at https etrel com charging solutions inch duo www etrel com Etrel d o o Pod jel ami 6 1290 Grosuplje Slovenia EU 2020 Etrel All rights reserved Etrel the Etrel l...