Cables
Installation
Turn the changeover valve into the correct
position
In buffer operation of the boiler, switching between the
heating circuit and the hot water tank is no longer
needed. Therefore, remove the actuator from the
changeover valve.
Fig. 10-19: Actuator for changeover valve
Turn the changeover valve manually so that the
flow line to the hot water tank is blocked. See the
following illustration.
Fig. 10-20: correct position of the changeover valve
The actuator is no longer required. You can
disconnect its cable from the circuit board and
leave it on the boiler.
10.5
Cables
Connecting the boiler to potential equalisation
The boiler must be connected to the potential equaliza-
tion of the boiler room or the building. Country-specific
regulations must be observed while doing this.
Fig. 10-21: Connecting the potential equalisation
The bottom of the boiler features holes to connect
the potential equalisation (minimum cross-
section 6 mm²).
10.6
Filling the heating system
Filling the heating system
Fill the boiler via the fill/drain valve. The current system
pressure is shown on the pressure gauge.
Содержание PelletsCompact
Страница 1: ...2020 07 21 EN 0000000061 V 022 1513 93003 003 PelletsUnit 7 15 kW Installation ...
Страница 41: ...Installation Network connection 41 ...
Страница 45: ...Electrical connections Overview of circuit boards 45 ...
Страница 49: ...Electrical connections PE C4 circuit board 49 ...
Страница 66: ...www eta co at ...
Страница 67: ......
Страница 68: ...www eta co at www eta co at downloads DOWNLOAD ...