3. INSTALLING MAG816
• Select the best location for the panel away from sources of heat, environmental dust
and potential water ingress, with an ambient temperature of between -5°C and + 40°C,
Figure 1.
• Undo the two secure bolts - Figure 2. Use the instrument supplied for the purpose in
the set (hexagonal tool No. 2).
• Open the front panel and disconnect the earth cables: from the 230 V clamps, from the
metal bottom clamps and from the chassis.
• Disconnect the indication ribbon cable.
• Remove the front panel by undoing the screws of the hinges - Figure 3. (
NB.
The
screws at the metal bottom can also be undone. What is special here is that there are
two plastic pads under the every hinge. These pads need to be placed back again under
the hinges when mounting the front panel.
)
• Select the input openings for the cables and place a plastic cap, provided with the panel
accessories, on those which are not going to be used, see Position 9 from the spare
parts kit on page 31.
• Perform an exposed or flushed mounting (option) - see items 3.1 and 3.2.
• Run all external cables into the box to establish connection
but do not connect them
at this stage yet. Run the mains cable through the chosen opening but keep it
away from the low voltage wirings.
• Connect the mains supply and earth to the main terminal block but
do not
switch the
main electrical supply on at this stage.
• Place the plastic lightpipe (see Positions 7, 11 and 15, page 31), provided with the
spare parts kit, at their designated locations on the main module, zone and/or sounder
expanders.
• Position the battery and secure it with the clamp - Figure 9, Position 1.
• Connect the zone and sounder circuits and program the panel according to the specific
application.
• Mount the front panel back onto the hinges and connect the indication ribbon cable and
the earth cables: to the 230 V clamps, to the metal bottom clamps and to the chassis.
• After all system programming and testing operation are complete, screw both secure
bolts with the help of the hexagonal tool supplied.