Assembly instructions
(Original)
BT / BM / BF Gearboxes
Doc. No. : 1002
Version 1 dated 18/10/2018
Page 8/11
After the motor has been inserted until the motor plate is in
contact with the gearbox flange, screw the motor to the
gearbox flange. Take care of the thread reach of the bolts.
The thread reach of the bolt shall be twice the length of the
nominal diameter of the bolt. (Figure 2)
6
Commissioning
CAUTION!
The commissioning may only be carried out by accordingly qualified trained per-
sonnel.
Before commissioning, all mechanical mounting parts and their fastening must be
checked. Check the screw tightening torques. Commissioning may only take place if
the machine complies with the provisions of the EC Machinery Directive. The moni-
toring and protective devices of the machine must not be put out of operation. In
addition to EMERGENCY STOP buttons, EMERGENCY STOP command devices, covers
and hoods, this also includes other protective devices such as sensors, light barriers
and acoustic or optical emergency signals. The security of the gearbox can only be
assured by the end product. Therefore, any commissioning with overridden protec-
tion equipment of the machine is not permitted.
DANGER!
Death or extremely serious injury / crippling caused by equipment in operation
without suitable safety or protective devices by the surrounding end product.
7
Operation
CAUTION!
The gearbox may only be operated by accordingly qualified trained personnel.
The gearbox may only be operated with active protective and monitoring equipment
of the machine.
Figure 2: Length of the
bolt