EP-2800 INSTALLATION GUIDE
8
Wye Installation
1. Cut hole in case
2. Connect green ground to the green ground connection of terminal block
3. Connect white neutral to the neutral terminal block.
4. Connect black phase a to phase a of the terminal block
5. Connect black phase b to phase b of the terminal block
6. Connect black phase c to phase c of the terminal block
7. Place phase, ground and neutral wires into conduit and feed to the panel
8. Connect green ground to the ground connection
9. Connect white neutral to the neutral bus.
10. Connect black phase a to phase a of the 100 a circuit breaker
11. Connect black phase b to phase b of the 100 a circuit breaker
12. Connect black phase c to phase c of the 100 a circuit breaker
* Ground is always connected to the neutral bus at the main service
Delta Installation:
1. Cut hole in case
2. Connect green ground to ground terminal block
3. Connect black phase A to phase A of the terminal block
4. Connect black phase B to phase B of the terminal block
5. Connect black phase C to phase C of the terminal block
6. Place phase wires into conduit and feed to the panel
7. Connect green ground to the ground connection
8. Connect black phase A to phase A of the 100 A circuit breaker
9. Connect black phase B to phase B of the 100 A circuit breaker
10. Connect black phase C to phase C of the 100 A circuit breaker
* Ground is always connected to the neutral bus at the main service