4-1 OVERVIEW
This section describes service and routine
maintenance of the SPS 4000. Replacement
parts referenced are available from Rosemount.
Refer to Section VI for part numbers and order-
ing information.
Install all protective equipment covers
and safety ground leads after equip-
ment repair or service. Failure to in-
stall covers and ground leads could
result in serious injury or death.
4-2 FUSE
REPLACEMENT
The SPS 4000 has a fuse on the power supply
board. Refer to Table 7-1 for replacement fuse
specifications. Perform the following procedure
to check or replace the fuse.
Disconnect and lock out power before
working on any electrical components.
a.
Turn off power to the system.
b.
Remove screw (22, Figure 4-1) securing
manifold cover lock (21) and remove the
lock.
c.
Remove manifold cover (28).
d.
Remove fuseholder (26) by pushing in the
top and turning 1/4 turn counterclockwise.
Remove fuse (25).
e.
After checking or replacing fuse (25), install
fuseholder (26) by pushing in the top and
turning 1/4 turn clockwise.
f.
Install manifold cover (28) and secure with
manifold cover lock (21) and screw (22).
4-3
BOARD REPLACEMENT
Perform the following procedure to replace
power supply board (23, Figure 4-1) or interface
board (31).
Disconnect and lock out power before
working on any electrical components.
a.
Turn off power to the system.
b.
Remove screw (22) securing manifold cover
lock (21) and remove the lock.
c.
Remove manifold cover (28).
d.
Remove two screws (32) attaching spacers
(35) to manifold (38).
e.
Being careful not to disconnect the board
wiring, carefully lift power supply board (23)
and interface board (31) from manifold (38)
and set aside. Do not lose o-rings (36) from
the bottom of spacers (35).
f.
For the board to be replaced, tag all leads
to simplify installation.
g.
If replacing the power supply board, refer to
Figure 4-2. Remove the line voltage input
leads from connector J7. Also, unplug cali-
bration gas 1 solenoid leads from connector
J5, calibration gas 2 solenoid leads from
connector J4, and pressure switch leads
from connector J2.
h.
If replacing the interface board, refer to
Figure 4-2. Remove the CAL INITIATE
leads from connector J3, CAL FAIL and IN
CAL leads from connector J4, and logic I/O
handshake connection from connector J5.
i.
Remove stop nuts (33, Figure 4-1), washers
(34), and screws (37) securing power sup-
ply board (23) and interface board (31) to
spacers (35).