4

Penberthy 

SErIES N6 GaGEcockS 

InstallatIon, operatIon and maIntenance InstructIons

4 InstallatIOn

Installation should only be undertaken by 
qualified, experienced personnel who are 
familiar with this equipment and have read 
and understood all of the instructions in this 
manual.
The user should refer to relevant technical 
data sheets or product proposal to obtain 
dimensional information for the specific size 
and model of gagecock set.

4.1 Mounting

1.  Prior to actual installation, turn handwheel 

or lever of each gagecock clockwise until 
stem closes against seat.

2.  Mount upper and lower gagecocks to vessel 

using PTFE tape on all male tapered pipe 
thread connections.

3.  Tighten vessel connections to a pressure 

tight joint making certain that sight glass 
connections are aligned vertically and to 
vessel centers as called for on application 
specification.

4.2 sight glass installation

1.  Turn upper gagecock counterclockwise 

(approx. ⅛ turn).

2.  Loosen glass packing nut to insure there is 

no compressive force on glass packing.

3.  Insert sight glass in upper gagecock sight 

glass connection.

4.  Tighten upper gagecock to original position 

while holding sight glass in position with 
upward force to insure its clearing of lower 
sight glass connection. check vertical 
alignment of gagecocks.

5.  Loosen glass packing nut on lower 

gagecock and pull glass down into lower 
gagecock sight glass connection to a 
positive stop.

6.  Tighten upper and lower glass packing nuts.

 note: 

in some circumstances, it may be 

necessary to remove glass packing nut, 
glass packing gland and glass packing, and 
mount them on sight glass prior to insertion 
of glass in upper and lower gagecock 
bodies. See Figure 1 for proper assembly 
sequences.

4.3 guard rod installation

Guard rods (two required) are assembled 
downward through upper gagecock with 
swaged portion on rods at the top. Bottoms of 
rods are positioned into respective holes in the 
lower gagecock.

5 OPeratIOn

5.1 Pre-operational check

1.  assure that all installation procedures have 

been completed.

2.  check to determine that all connections are 

pressure tight.

5.2 hydrostatic test

1.  Take all precautions necessary to handle 

the possibility of leakage during the test.

2.  Hydrostatic pressure test all installations to 

100 psig (690 kPaG) and correct any leakage 
before proceeding.

5.3 Operating

Gagecock assemblies should be brought 
into service slowly. The tubular glass used in 
Penberthy gagecocks is tempered and can 
stand minimal thermal shock and mechanical 
stress.
To avoid excessive thermal shock or 
mechanical stress on the tubular glass, the 
connecting gagecocks should be opened 
slightly and the tubular glass temperature and 
pressure allowed to equalize slowly with the 
vessel.
If the gagecocks are furnished with ball checks, 
the gagecocks must be opened all the way after 
the pressure and temperature have equalized 
to permit operation of the automatic ball check 
in the event of tubular glass breakage.

6 MaIntenanCe

Maintenance should only be undertaken by 
qualified, experienced personnel who are 
familiar with this equipment and have read and 
understood all the instructions in this manual.
During system shut down, the gagecocks 
should be left open to permit the gage to lose 
pressure and cool with the rest of the system.
Failure to leave the gagecocks open during 
system shut down will trap high pressure fluid 
in the gage.

WarnIng

Do not proceed with any maintenance unless the 
gage has been relieved of all pressure or vacuum, 
has been allowed to reach ambient temperature, 
and has been drained or purged of all fluids. 
Failure to follow any instructions could result in 
severe personal injury or property damage.

Содержание PENBERTHY N6 Series

Страница 1: ...r products buildings personnel or property by reason of the installation or use of its products This is Emerson s sole warranty and in lieu of all other warranties expressed or implied which are hereby excluded including in particular all warranties of merchantability or fitness for a particular purpose This document and the warranty contained herein may not be modified and no other warranty expre...

Страница 2: ...being gaged tends to surge in a rapid manner the ball checks could tend to give a false level reading or seat accidentally Series N6 gagecocks are not suitable for steam water applications unless they are furnished with one of the following optional features 1 Non automatic gagecocks ball checks removed from both upper and lower gagecocks 2 Automatic gagecocks vertical rising ball check and ball i...

Страница 3: ...Under no circumstances should these design ratings or application data be exceeded Exceeding design ratings or application data may cause severe physical injury or property damage 3 2 User s rating inspection The user should confirm that 1 The gagecock set model number and pressure temperature rating stamped on nameplate 163 conforms to the description on the user s purchase order 2 The operating ...

Страница 4: ...nstallation Guard rods two required are assembled downward through upper gagecock with swaged portion on rods at the top Bottoms of rods are positioned into respective holes in the lower gagecock 5 Operation 5 1 Pre operational check 1 Assure that all installation procedures have been completed 2 Check to determine that all connections are pressure tight 5 2 Hydrostatic test 1 Take all precautions...

Страница 5: ...seat surface follow Disassembly steps a through f Renew seat by using a fine lapping compound and a mandrel with the same size shape and seat angle as the stem Flush gagecock body clean and reassemble by following steps a through f of Reassembly Note Series N6 gagecocks have an integral seat The gagecock body must be replaced when the seat becomes worn or damaged beyond repair 3 Signs of leakage a...

Страница 6: ... appropriate federal and industry regulations the user must determine the extent of preparation and treatment the gagecock must incur before its disposal A Material Safety Data Sheet MSDS may be required before disposal services accept certain components Metal glass and polymers should be recycled whenever possible Refer to order and relevant technical data sheets for materials of construction 9 T...

Страница 7: ...11 Body 15 Ball 17 Stem 18 Retainer stem packing 25 Packing stem 26 Nut stem packing 28 Handwheel 163 Nameplate 100 Screw Recommended spare parts Item Description Min qty 18 Retainer stem packing 2 25 Packing stem 2 26 Nut stem packing 1 34 Packing glass 2 35 Retainer glass packing 2 37 Nut glass packing 1 48 Glass 1 Recommended maximun quantities should provide spare parts for 10 of the gagecocks...

Отзывы: