M2CP Electrical Hook Up
2.1
Electrical Hook Up
Step 1.
Move valve to mid-position by handwheel. This will allow sufficient time to
stop actuator in case of improper hook-up or reversed incoming power
voltage phases.
Step 2.
Identify a means of removing power from actuator during check out.
Be sure no erroneous remote control signal can be received causing
actuator to energize.
Step 3.
Energize Open control to check operation of contactor and pushbuttons.
Open controls must move valve in Open direction. If valve Closes, actuator
must be stopped and power input must be rewired.
CAUTION
If voltage is improperly phased, Torque and Position Limit Switches are not in circuit to
protect valve.
Step 4.
Seal all field conduit entries in accordance with National Electric Code.
Section 2: M2CP Electrical Hook Up