All plug-in modules and blank plates are part of the 
fire enclosure and must be removed only when a 
replacement can be added immediately. The system 
must not be run without all parts in place.

A controller or a shelf must be operated only 
from a power supply input voltage range of 
100–240 VAC, 50–60 Hz.

Each component is intended to operate with 
two working power supplies installed. 

Provide a suitable power source with electrical 
overload protection.

A safe electrical earth connection must be pro-
vided to the power cord. Check the grounding 
of the power sources before applying power.

The plug on each power supply cord is used 
as the main disconnect device. Ensure that the 
socket outlets are located near the equipment 
and are easily accessible.

Permanently unplug the unit if you think it is 
damaged in any way and before moving it. If 

the unit is powered by multiple sources, discon-
nect all supplied power for complete isolation.

The power connections must always be 
disconnected prior to removal or replacement 
of a power supply module from any of the 
components in the system.

A faulty power supply module must be replaced 
within 24 hours.

Do not lift system components by yourself. A 
controller weighs 66 lbs (30 kg) and an ES20 
expansion shelf weighs 78 lbs (35.5 kg). 

Do not lift an ES20 by the handles on the PSU/
cooling module. The handles are not designed 
to support the weight of the populated shelf.

To comply with applicable safety, emission, 
and thermal requirements, covers must not 
be removed and all bays must be fitted with 
plug-in modules.

Load the rack beginning at the bottom to 
prevent the rack from becoming top-heavy.

Do not extend components on slide rails until 
you have loaded at least three or more similarly 
weighted items in the rack, or unless the rack 
is bolted to the floor or overhead structure to 
prevent tipping.

Warning: 

When the system is in normal use, the 

system controller top cover must be secured by 

rotating the lock 90° to the locked position to prevent 

users or operators from accessing the service areas.

Caution: 

If the system is used in a manner not 

specified by the manufacturer, the protection provided 

by the equipment may be impaired.

Caution: 

The RJ45 sockets on the motherboard/PCI 

cards are for Ethernet connection only and must not be 

connected to a telecommunications network.

ESD PrEcautionS

Data Domain recommends that you fit and check a 
suitable antistatic wrist or ankle strap and observe 
all conventional ESD precautions when handling 
plug-in modules and components.

Safety

1.  Unpack the Data Domain system.

 

A system consists of a DD660 

controller with 12 TB internal storage and up to 24 TB raw storage in 
optional ES20 expansion shelves.

Open the packing boxes for the controller and optional expansion shelf 
or shelves.

Remove the accessories and rack mount kits for all system components.

2.  Install the appropriate rack mounting hardware

 for the 

controller and ES20s into a 19-inch, four-post rack. Ensure that the rack is 
securely anchored to prevent tipping. Load the rack or cabinet, beginning 
at the bottom to prevent the rack from becoming top-heavy. Be sure to 
plan appropriate vertical space to accommodate the 2U controller and 3U 
for each ES20 expansion shelf. 

See the instructions included with the slide rails. See Figure 1.

The ES20 slide rails also include rack installation instructions.

3.  Install the controller and expansion shelves in the rack.

Remove the controller and ES20s from the shipping boxes.

Remove the bezel from each component.

Install each component horizontally on the corresponding slide rails 
and slide in the rack in the order described in the 

Expansion Shelf 

Hardware Guide

. Be sure one person is at each side of each of the 

component to guide it into the rail ends. 

Secure the components in the rack with the thumb screws.

4.  Connect ES20 shelves to the controller.

 Connect the controller’s 

SAS ports to the ES20 shelves based on the cabling diagrams for expan-
sion shelf connectivity. See Figures 6 and 7. Use the cable management 
hardware provided to organize all cables.

5.  Connect an administrative console.

 Attach a serial console to the 

controller’s serial port, or use KVM connections to connect monitor (VGA 
port), keyboard and mouse. See Figure 2.

6.  Enable data transfer connectivity. 

Repeat for each connection. 

Ethernet connection:

 To use 1 Gb copper Ethernet, attach a Cat 

5e or Cat 6 copper Ethernet cable to an RJ45 Ethernet network port 
(start with eth0 and go up) on the controller. Attach the other end 
to an Ethernet switch or to an Ethernet port on your server. For 1 Gb 
fiber Ethernet, use multimode fiber cables with LC connectors. For 10 
Gb copper Ethernet with a CX4 connector, use an IEEE draft standard 
802.3ak / D5.3 compliant cable or a Data Domain CX4 cable. Not all 
CX4 cables qualify. For 10 Gb copper Ethernet with SFP+ connectors, 
use a qualified SFP+ copper cable. For 10 Gb fiber Ethernet, use MMF- 
850nm cables with LC duplex connectors. See Figure 2.

Fibre Channel connection:

 Attach a Fibre Channel fiber optical 

cable (LC connector) to a VTL HBA port on the controller, and attach 
the other end (LC connector) to a Fibre Channel switch or to a Fibre 
Channel port on your server. See Figure 2 for PCI card locations for the 
VTL HBAs.

7.  Provide redundant power to the system.

Controller power:

 Connect power cables to both receptacles and set 

the power cable retention clips. See Figure 2.

ES20 power: 

Connect power cables to both receptacles and set the 

power cable retention clips. See Figure 5.

8.  Turn the system on. 

Power on any ES20s before the controller.

ES20 power:

 Turn the power switch to 

on

 for each of the two power 

supplies for each ES20 expansion shelf. See Figure 5.

Wait approximately 3 minutes after all expansion shelves are turned on.

Controller power:

 Push the power button. See Figure 3.

Attach the bezels.

9.  Collect the information needed for installation.

 Enter the 

information in section 2 on the other side of this sheet.

 

install Hardware

1

The steps for a complete installation and configuration are:

1. 

Install Hardware

2. 

Define the Data Domain system information for your site

3. 

Perform initial system configuration

4. 

Configure the system for data access

5. 

Configure optional software

6. 

Perform optional additional system configuration

installation and Setup Steps

1

5

4

3

2

6

installation and Setup Guide