General

This leaflet contains installation instructions for the REX and REX2-EA solid-state, residential 
electricity meters (referred to as “REX” within this IL) with the following form factors:

self-contained: Forms 1S, 2S, and 12S

transformer-rated: Forms 3S and 4S

All meters are calibrated and sealed before shipment. For proper installation, accuracy, and 
maximum life of the meters, use the following procedures.

WARNING

!

Use authorized utility procedures to install and service metering equipment. Dangerous 
voltages are present. Equipment damage, personal injury, or death can result if safety 
procedures are not followed.

WARNING

!

When using the REX meter with the internal service control switch, follow authorized utility 
procedures to reconnect electrical service. Property damage, personal injury, or death can 
result if proper safety precautions are not followed.

Installing the REX Meter

1.

Make sure the meter to be installed matches the service type (that is, form), current, 
capacity, voltage, and service socket.

2.

Check the socket and verify that the wiring is correct. See “Internal Wiring Diagrams” on 
page 2 a
nd “Installation Wiring Diagrams” on page 3 for wiring diagrams.

3.

Make sure that the voltage disconnect or test link on the back of the meter is closed, if 
installed.

4.

Line up the meter blades to the socket jaws and rock the meter into place. Make sure 
that the meter is in the upright position.

5.

Make sure the LCD turns on and the energy use indicator flashes if load is present.

The LCD has two pulse arrows. The arrow pointing to the left indicates energy received; the arrow 
pointing to the right indicates energy delivered. For more information, see the technical manual for 
your meter.

6.

Apply all seals and record any necessary information.

Содержание REX2

Страница 1: ...al service control switch follow authorized utility procedures to reconnect electrical service Property damage personal injury or death can result if proper safety precautions are not followed Installing the REX Meter 1 Make sure the meter to be installed matches the service type that is form current capacity voltage and service socket 2 Check the socket and verify that the wiring is correct See I...

Страница 2: ...gerous voltages may be present if current transformer secondaries are open circuited while the transformer is energized Equipment damage personal injury or death can result if circuit closing devices are not used Form 1S PS PS Form 2S Alternate positions of movable potential terminal PS Form 3S PS Form 4S 31H05 PS Form 12S Alternate positions of movable potential terminal ...

Страница 3: ...t if circuit closing devices are not used N 1 L O A D 1 N 1 N Form 1S 1 phase 2 wire self contained 20E01 1 2 N L O A D 2 N 1 N 2 1 Form 2S 1 phase 3 wire self contained 20E01 N 1 L O A D 1 N 1 N Form 1S service control switch 1 phase 2 wire self contained 13L07 Service control switch Form 3S 1 phase 3 wire 1 CT no VTs 11G03 1 2 N N 2 1 CIRCUIT CLOSING DEVICE Form 3S 1 phase 2 wire 1 CT no VTs 11G...

Страница 4: ...N N 2 1 Form 12S service control switch 2 phase 3 wire wye self contained 13L07 Service control switch 120 208 service voltage only 120 208 service voltage only FCC and Industry Canada Compliance Compliance Statement Part 15 19 This equipment complies with Part 15 of the FCC Rules and with RSS 210 of Industry Canada Operation is subject to the following two conditions 1 This device may not cause h...

Отзывы: