9
EN
Follow the below instructions for the installation of the G Control PM power meters. (PV generation and
home consumption)
Disconnect the main switch of the consumer unit prior to the device installation.
Disconnect the inverter and the PV generation before the device installation.
Warning:
The G Control PM is valid only for single-phase installations.
The G Control PM device is prepared to be installed in the consumer unit of your home.
a.
Install the device on the DIN rail in the consumer unit of your home.
b.
Connect the device using the appropriate wiring to a 230 V power supply.
c.
Connect the clamp energy meter to the G Control PM device and embrace:
1. Home consumption meter. The main cable at the output of the main switch to record the total
energy consumption.
Warning:
The home consumption meter is installed measuring the total consumption of the
home as it is shown in the diagram of the previous page. It must not be installed in the same point
than the company smart meter.
2. PV Generation meter. The line connection cable from the PV inverter to the consumer unit of
your home to register the PV generation.
2.2. G Control Hub USB Smart-box installation.
Connect the G Control Hub USB Smartbox to any USB Port. Can be the router USB port or any other like a
phone charger.
RF SIGNAL