TESTING THE LOOP
To make sure the installation of EK components was
successful, we recommend you perform a leak test for 24
hours.
When your loop is complete and filled with coolant,
connect the pump to a PSU outside of your system. Do not
connect power to any of the other components. Turn on
the PSU and let the pump run continuously. It is normal for
the coolant level to drop during this process as air collects
in the reservoir.
Inspect all parts of the loop, and in the eventuality that
coolant leaks, fix the issue and repeat the testing process.
Ensure that all hardware is dry before the system is
powered on in order to prevent any damage.
Содержание EK-Quantum Kinetic TBE D5 PWM
Страница 1: ...INSTALLATION MANUAL EK Quantum Kinetic TBE D5 PWM PUMP RESERVOIR COMBO...
Страница 4: ...4 ALTERNATIVE DAMPER STEP 1 Pyramids must be facing UP...
Страница 6: ...6 USING EK HD TUBE STEP 1...
Страница 8: ...8 USING TOP PORT AS INLET Internal Tube EK Quantum Kinetic TBE D5...
Страница 14: ...14 ATTACHING FITTINGS EK Fittings INLET OUTLET EK Plugs G1 4 EK Plug G1 4...
Страница 16: ...16 CONNECTING THE D RGB LED STEP 1 D RGB Header RGB Header...
Страница 19: ......