Installing the SwitchAir
1.
Before installing SwitchAir; Velcro tie the network switch power cords to power supply handle toward
the centre of the switch. This will dress the switch power cords toward the centre where the SwitchAir
brush strip is located - allowing a good SwitchAir to switch seal. The SwitchAir brush strip has ample
width to allow you to just direct the switch power cords toward the centre. Power cords from one
switch are allowed to pass through the brush strips of a unit below. Example shown of two networks
switches would require two SwitchAir units.
2.
Before installing SwitchAir; remove the lower network switch mounting screw from each side of the
rack front rails (if necessary). Save these screws to be used in the next step for mounting the SwitchAir.
The network switch upper screw will remain fastened.
3.
SwitchAir is not in a fully extended position when shipped from the factory. Pull evenly on the
chassis mounting tabs for the desired depth. Insert SwitchAir into the open rack space at the same U
height as the switch. As SwitchAir is pushed into the space, the SwitchAir Rail Tabs will engage the
network switch rails for support during installation. Keep pushing the SwitchAir into the space until
the SwitchAir front mounting flanges are flush with the rack front rails. Reinstall the screws that were
removed previously. Installation is now complete.