2.5 Setup Process
The setup and deployment process involved for the CIPR generator involves locating the machine on a
level, suitable terrain, connecting earth ground and fuel source, and connecting electrical distribution.
Before using the unit, be sure to read and understand all of the instructions. This equipment was
designed for specific applications; DO NOT modify or use this equipment for any application other
than which it was designed for. Equipment operated improperly or by untrained personnel can be
dangerous.
Before starting visually inspect the unit for leaks or damage. A complete visual inspection of all
engine, generator, and power distribution connections
Quick Setup Guide:
1. Inspect the engine, intake, exhaust, cooling system, to verify that the engine is fully assembled
and not in the process of being serviced.
2. Ensure the engine is free to turn without obstruction.
3. Check that all safety guards are in their correct position and secure.
4. Check that the coolant level in the radiator overflow bottle is between "Add" and "Full".
5. Check that the oil level on the dipstick is between "Add" and "Full".
6. Check that the fuel supply is connected, shut-off valves are open, and there are no leaks.
7. If an LPG fuel system is being used, verify that there is fuel in the cylinder/tank.
8. If a natural gas fuel system is being used, verify that the correct fuel supply pressure is being
supplied to the engine.
9. Read and understand ALL safety sections at the beginning of this manual.
10. Ensure all maintenance procedures are up to date.
11. Ensure unit is set up on firm and level ground, with the area around the generator clean
12. Ground unit in accordance with local grounding requirements through ground lug connection on
the distribution panel, the unit ground is marked with the IEC 60417, No 5019 ground symbol
13. Warn personnel on site of pending startup
14. Connect the fuel source in accordance with local guidelines and safety requirements, note, we
recommend that the fuel pressure is checked during each initial startup and new site
commisioning, it is essential that primary, secondary or vaporizer regulators are tuned and set
for this equipment (7-11” WC inlet pressure, even under load)
15. Ensure main and secondary circuit breakers are in the OFF or Green position
16. Check engine oil and coolant levels, visually inspect the engine for leaks, inspect belts, electrical
connections and wiring out the generator enclosure
17. Inspect all electrical connections; repair or replace any that are cut, worn, or bare. This includes
inspecting cords external to the generator connected to the load-use safe electrical practices in
accordance with local guidelines and best practices
19
Содержание CIPR-15Z NG/LP
Страница 10: ...2 2 Product Specifications 10 ...
Страница 12: ...2 3 Product elements 12 ...
Страница 14: ...14 ...
Страница 15: ...15 ...
Страница 16: ...16 ...
Страница 17: ...Alarm Icons 17 ...
Страница 18: ...Note See Deep Sea 4510 MKII user manual for complete details on operation and troubleshooting 18 ...
Страница 25: ...25 ...
Страница 26: ...THIS PAGE INTENTIONALLY LEFT BLANK 26 ...