Fig. 1: Recommended stripped lengths (inside terminal box)
(1) supply line (2) control and relay line

4.3.2 Terminal connection data

Supply line

min.

max.

Rigid cable cross-
section

0.2 mm²

4 mm²

Flexible cable cross-
section

0.2 mm²

4 mm²

AWG/kcmil cable
cross-section

24

12

Wire-end ferrules with
insulating collar,
in accordance with
DIN 46228-4 for
flexible cable

0.25 mm²

4 mm²

Wire-end ferrules
without insulating
collar,
in accordance with
DIN 46228-1 for
flexible cable

0.25 mm²

4 mm²

NOTE

The cable and cable cross-section must be selected taking into
account the max. starting current of the drive and the type of
cable routing (see Chapter 4.2.2 Supply connection and fuses)

Control and relay cables

min.

max.

Rigid cable cross-
section

0.2 mm²

1.5 mm²

Flexible cable cross-
section

0.2 mm²

1.5 mm²

AWG/kcmil cable
cross-section

24

16

Wire-end ferrules with
insulating collar,
in accordance with
DIN 46228-4 for
flexible cable

0.14 mm²

0.75 mm²

Wire-end ferrules
without insulating
collar,
in accordance with
DIN 46228-1 for
flexible cable

0.25 mm²

1.5 mm²

NOTE
Crimping and pressing forms of the wire-end ferrules

For flexible control and relay cables, from a cable cross-section
of 1.0 mm², a trapezoid crimp is required to ensure correct
installation on the connector.

Fig. 2: Trapezoid crimp

4.3.3 Connect cables to terminals

WARNING
Live terminals and connections even with device
switched off

Electric shock
→ Wait five minutes after disconnecting the voltage at all poles

before opening the device.

;

Open the terminal box.

;

Remove the cap from the cable gland.

;

Only remove caps where cables are fed in.

Fig. 3: Installing the connectors in the terminal box. The connectors
must engage properly.

;

Depending on the cable diameter, the seals included in the terminal
box must be inserted into the cable gland if necessary.

;

Route the cable(s) (not included in the scope of delivery) into the
terminal box.

;

Ensure separate routing of the supply cable(s) and the cables for
status contact and control interface. Depending on the requirements for
the end device, the physical separation of these cables in the terminal
box may be mandatory. Use the partitions inside the terminal box as
an aid to routing for this purpose.

;

First connect the protective earth "PE". Tightening torque 3.5 ±0.4 Nm

Item no. 1170000644 · ENU · Change 238377 · Approved 2021-12-16 · Page 9 / 17

ebm-papst Mulfingen GmbH & Co. KG · Bachmühle 2 · D-74673 Mulfingen · Phone +49 (0) 7938 81-0 · Fax +49 (0) 7938 81-110 · [email protected] · www.ebmpapst.com

Содержание VBS0355CTRLS

Страница 1: ...ice to carry out a test run and to perform work on the electrical installation 1 3 Basic safety rules 1 1 3 Basic safety rules The safety hazards associated with the device must be assessed again foll...

Страница 2: ...em machine wait until all parts have come to a standstill DANGER Ejected parts Missing protective devices may cause balancing weights or broken fan blades to be ejected and cause injuries Take appropr...

Страница 3: ...r 3 2 Nominal data Operating the device with all protective devices Following the operating instructions Improper use In particular operating the device in the following ways is prohibited and could b...

Страница 4: ...ax clearance for screw 20 mm 3 Cable diameter min 4 mm max 10 mm tightening torque 4 0 6 Nm The tightening torque is designed for PVC cables If the cable materials are different the tightening torque...

Страница 5: ...k factor 145 1 Fastening holes for FlowGrid 00400 2 2957 not included in scope of delivery are provided and must be subsequently opened as required Item no 1170000644 ENU Change 238377 Approved 2021...

Страница 6: ...sions must be requested from ebm papst If other air conduction geometries are used on the installation side the ebm papst evaluation loses its validity the conformity must be confirmed again The produ...

Страница 7: ...s the responsibility of the installation engineer or operator owner of the device to ensure if necessary after consultation with the network operator that this device is only connected to a connection...

Страница 8: ...r required fuses line protection only no equipment protection Nominal voltage Fuse Automatic circuit breaker Cable cross section Cable cross section VDE UL VDE mm AWG 3 PE AC 380 480 VAC 16 A 15 A C16...

Страница 9: ...re end ferrules For flexible control and relay cables from a cable cross section of 1 0 mm a trapezoid crimp is required to ensure correct installation on the connector Fig 2 Trapezoid crimp 4 3 3 Con...

Страница 10: ...awing 4 3 4 Cable routing Water must be prevented from reaching the cable gland along the cable NOTE Damage caused by moisture penetration Moisture can penetrate into the terminal box if water is cons...

Страница 11: ...aracteristic curve P1 IN SELV CON2 IO3 Function parameterizable see Optional interface functions table Factory setting Analog output 0 10 V max 5 mA function Fan modulation level Characteristic curve...

Страница 12: ...SELV D159 0 Ain2 0 10V PWM analog input D159 2 Ri 100K characteristic curve parameterizable f PWM 1k 10KHz SELV Ain2 4 20mA analog input Ri 125R characteristic curve parameterizable SELV D159 3 Din3 a...

Страница 13: ...inal operating instructions 4 6 Equivalent circuit diagrams Item no 1170000644 ENU Change 238377 Approved 2021 12 16 Page 13 17 ebm papst Mulfingen GmbH Co KG Bachm hle 2 D 74673 Mulfingen Phone 49 0...

Страница 14: ...1 Suppression of speed ranges Speed ranges in which the vibration velocity in the motor fan is too high must be avoided in continuous operation Excessive vibration velocities can be caused by resonan...

Страница 15: ...pply Attention The error message resets automatically Device restarts automatically without warning Faulty connection Isolate from supply correct connection see connection diagram Broken motor winding...

Страница 16: ...ening diameter on the motor support plate in the direction of the motor axis of rotation and perpendicular to this Fig 5 Example illustrating vibration measurement The arrangement of the sensors depen...

Страница 17: ...dations for ecological disposal of the product and its components 6 5 1 Country specific legal requirements NOTE Country specific legal requirements Always observe the applicable country specific lega...

Отзывы: