9
Instruction Booklet
IB02201004E
Effective October 2017
Revision #4
Instructions for installation, operation, and
maintenance of 38 kV type VacClad-W,
150 BIL switchgear indoor housings
EATON
www.eaton.com
D . Movement of the breaker from the Connect position to the
Disconnect position:
1 . Before the breaker can be moved from the Connect position
to the Disconnect or Test position, the breaker must be open .
2 . Insert the levering crank onto the hex drive nut on the racking
screw . In order to engage the hex drive nut, you must push
the safety slider in and out of the way of the hex nut .
otee:
N
If the breaker is closed, you will not be able to push the safety slider in
to engage the hex drive nut . You must trip the breaker by means of either the
Open pushbutton on the front of the breaker or electrically using the control
circuit .
3 . Rotate the levering crank in a counter-clockwise direction
until the breaker is in the Test of the Disconnect position .
otee:
N
The secondary plug on the compartment pan assembly is automati-
cally disengaged from the breaker secondary plug .
Step 10: Test the breaker and cell interface per IB3A74792 .
Step 11: Check the drawout transformer drawers in the auxiliary com-
partments .
A . Unbolt and remove the front covers of the auxiliary compart-
ments . The covers are removed by lifting upward and outward
toward the user (see Figures 6 and 7) .
B . The transformer drawers are shipped installed in the switchgear
in the Disconnect position . There are yellow shipping braces
located in the auxiliary compartments . This bracing secures
the transformer drawer to the cell for shipping purposes only .
Remove these braces and angles (see Figure 7) .
C . Remove the transformer drawers from the auxiliary compart-
ments . Refer to the portable lift device instructions in the
optional accessories section of this document for proper removal
of the drawers from the units prior to performing the following
actions . After removing the drawers, check for any damage to
the transformers, transformer fuses and fuse tubes, drawers,
and cell parts .
Figure 6. Auxiliary Compartment with Front Cover Installed.
Cover Interlock Bracket
Cover Guide
Racking Cover Plate
Viewing Window
Cover Guide
Perimeter Bolting
Cover Guide
Figure 7. Auxiliary Compartment with Cover Removed and
Drawer in the Disconnect Position.
D . The voltage transformer fuse is an integral part of the trans-
former . The fuse is located inside of a fuse tube mounted on top
of the transformer . The transformer(s) are mounted on a drawer
(see Figure 8) . Check the fuses for continuity . At one end of the
fuse tube is a contact spring and at the other is a contact plate .
Continuity can be checked between the two ends . See the
Transformers and primary fuses section of this manual for direc-
tions on how to gain access and replace fuses .
NOTICE
DO NOT HANDLE THE FUSE TUBES FOR PURPOSES OTHER THAN
CHANGING OUT FUSES. DOING SO, MAY CAUSE DAMAGE TO THE FUSE
TUBES AND MATING PARTS.
E . Installation of the transformer drawer into auxiliary compartment:
1 . Confirm that the transformer drawer is in the fully retracted
position prior to moving it into the compartment . The drawer
is fully retracted when the upper-half section of the drawer
is butted up against the lower-half section of the drawer (see
Figure 9) .
2 . Refer to the portable lift device instructions in the optional
accessories section of this document for details on lifting and
moving transformer drawers using the portable lifter . Move
the drawer to its location with a portable lifting device for
upper compartments, or roll it to its location directly on the
floor for lower compartments .
NOTICE
DO NOT HANDLE THE FUSE TUBES LOCATED ON TOP OF THE
TRANSFORMERS WHILE MOVING IN THIS MANNER. THIS MAY CAUSE
DAMAGE TO THE FUSE TUBES AND MATING PARTS.
Cover
Interlock Link
Cover
Guide
Cover Guide
Cover Guide
Safety Shutter Closed
Drawer Release
Handle
Drawer Safety Plate