3. STORAGE

The switchgear must be protected from the rain, 
and the humidity conditions should be as follows: 

The mean relative humidity value, measured over a 
period of 24 hours, must not exceed 95%. 

The mean water steam pressure value, measured 
in a period of 24 hours, must not exceed 2.2 kPa. 

The mean relative humidity value, measured over a 
period of one month, must not exceed 90%. 

The mean water steam pressure value, measured 
in a period of 1.8 hours, must not exceed 1.8 kPa.

During transport, vibrations caused by external
factors or seismic movements must be insignificant.

Ambient air temperature should not exceed 40 ºC
and its mean value, measured in a period of 24 hours,
should not exceed 35 ºC.

The ambient air temperature should not drop
below - 5 ºC. There are also cubicles with storage
temperature up to - 40 ºC.

The switchgear must be protected from direct solar
radiation.

Maximum altitude is 2000 m.

The environmental air must not have any significant
contamination from dust, smoke, corrosive and/or
inflammable gases, vapours or salt.

Any other conditions must be notified beforehand, since the equipment must be factory adjusted to the 
atmospheric pressure at the final destination or during transport.

Otherwise, the manometer needle may indicate an incorrect value, even if the equipment’s internal gas pressure 
is correct.

Storage must always be INDOORS, with the following conditions recommended:

If it needs to be stored, the equipment must be placed on dry ground or on top of damp-proof insulating material, 
still in its original packaging.

After prolonged storage, clean all the insulating parts carefully before commissioning the equipment. The 
enclosure should be cleaned with a clean, dry lint-free cloth.

!

Ulusoy URING12-24 - LLF - SF  Insulated Compact RMU Switchgear with Fuse User Manual

 May 2020 www.eaton.com 

3

6

Содержание Ulusoy URING12-24 F - SF6

Страница 1: ...Ulusoy URING12 24 LLF SF Insulated Compact RMU Switchgear with Fuse User Manual 12 24kV 200 630A 21kA 3s 6 www eaton com...

Страница 2: ...G 6 PHASE CONFORMITY TEST 6 CABLE TEST 6 8 1 1 Closing the Switchgear Door 7 8 1 2 Opening the Earthing Switch 8 8 1 3ChargingSpring 8 8 1 4 Closing the LBS 9 8 2 CUTTING ENERGY 9 8 2 1 Opening the LB...

Страница 3: ...ot alter or damage the characteristics of the equipment or its essential components Service conditions must be compatible with the equipment rating The equipment must be operated strictly in accordanc...

Страница 4: ...or on a pallet depending on the type of handling involved To handle assemblies of up to 5 functional units one of the following methods must be used Using a forklift truck or pallet jack Lifting using...

Страница 5: ...C The switchgear must be protected from direct solar radiation Maximum altitude is 2000 m The environmental air must not have any significant contamination from dust smoke corrosive and or inflammabl...

Страница 6: ...3 way design URING12 24 RMU can be designed up to 5 way unit as extensible or non extensible system Switching device in URING12 24 is three positioning close openearthed LBS It has high number of swi...

Страница 7: ...ting Handle Remote Controller Button optional 125 236 110 110 110 110 110 110 287 372 6 DIMENSIONS 861 1240 1642 Ulusoy URING12 24 LLF SF Insulated Compact RMU Switchgear with Fuse User Manual May 202...

Страница 8: ...able faults Turn the breaker ON Turn the disconnector ON Turn the earthing disconnector OFF Open the switchgear front cover Place the cable test device Turn the earthing disconnector ON Perform the re...

Страница 9: ...r Door Put the bottom side of the door to the switchgear Pull the door down Push the door towards the switchgear The door is now closed Ulusoy URING12 24 LLF SF Insulated Compact RMU Switchgear with F...

Страница 10: ...8 1 3 Charging Spring Insert the handle to the spring charging hole Turn it anti clock wise to charge the spring and remove the handle Find manual motor selection button Turn it from manual to motor...

Страница 11: ...ess Opening O button to close Check the position indicator for close position Check the position indicator for open position Put the lever into the earthing switch lever hole Rotate the lever in the d...

Страница 12: ...k the position of the earthing switch It must be in close position now 8 2 3 Opening the Switchgear Door Pull the door down Push the door upwards 10 Ulusoy URING12 24 LLF SF Insulated Compact RMU Swit...

Страница 13: ...6 Remove the blown fuse 2 Insert the handle and turn it anti clock wise 9 MV FUSE REPLACEMENT 7 Replace the new fuse make sure that striker pin looks upwards 8 Tighten the contact screw by screwdriver...

Страница 14: ...lock wise and make sure push on installation Elbow connector interface A for transformer protection connection T connector interface C for incoming outcoming connection 10 CABLE CONNECTION 12 Ulusoy U...

Страница 15: ...EAR Modular Switchgear are combined by using 6 pieces of M8x30 bolt Prior to assembly silicon crossing bushings and contact holes must be cleaned well Ulusoy URING12 24 LLF SF Insulated Compact RMU Sw...

Страница 16: ...n is to improve the quality of life and the environment through the use of power management technologies and services We provide sustainable solutions that help our customers effectively manage electr...

Отзывы: