INSTALLING OPTIONS AND ACCESSORIES
Eaton
Power Xpert 9395P-600 (380V-600V) UPS Installation and Operation Manual
S
P-164000710 Rev 1
www.eaton.com/powerquality
5-2
5.1
Installing an Optional Hot Sync CAN Bridge Card
As an option, a Hot Sync Controller Area Network (CAN) Bridge Card, shown in
Figure 5‐1, can be installed to provide connectivity for operational mode control of a
parallel system. In addition, this card can be used to connect optional system
monitoring devices, such as a Remote Monitor Panel II, a Relay Interface Module II,
or a Supervisory Contact Module II to the UPS.
Plug-in Terminal
Block J3
Figure 5‐1. Hot Sync CAN Bridge Card
NOTE
Only one Hot Sync CAN Bridge Card can be installed in the UPS. Multiple CAN cards are not
supported and will cause system conflicts.
To install the card:
1.
Verify the UPS system is turned off and all power sources are removed. See
Chapter 7, “UPS Operating Instructions,” for shutdown instructions.
2.
Unfasten the front door latch and swing the door open (see Figure 4‐1).
3.
Install the Hot Sync CAN Bridge Card into an open X-Slot communication bay on
the front of the UPS. See Figure 4‐18 and Figure 4‐24 for X-Slot communication
bay locations.
To locate the appropriate terminals on the Hot Sync CAN Bridge Card, see
Figure 5‐2 and Table 5‐1.