INSTALLATION
EATON
Powerware
®
BladeUPS
®
Bar Installation Guide
S
164201723 Rev P01
10
NOTE
Verify that the bar is secure as shown in Figure 4. The sheetmetal at the base of the
bar should be below the tab on the wireway floor.
12.
Secure the bar to the wireway with three M6
×
12 hex bolts. Install
the bolts from the
front
of the rack. See Figure 5. Torque the bolts
to 5.1
±
0.8 Nm (45
±
7 lb in).
13.
Reinstall the base bracket removed in Step 10. Install the bolts from
the
front
of the rack. See Figure 5. Torque the bolts to 5.1
±
0.8 Nm
(45
±
7 lb in).
NOTE
Do not change the original orientation of the base bracket. Verify that the threaded
holes mount to the rack, not to the bar.
Rear of Rack
Front of Rack
Base Bracket
M6
×
12 Hex Bolts
(3 places)
Figure 5. Bar Base Installation
Содержание Powerware BladeUPS Bar
Страница 1: ...Powerware BladeUPS Bar Installation Guide...
Страница 4: ...TABLE OF CONTENTS EATON Powerware BladeUPS Bar Installation Guide S 164201723 Rev P01 ii...
Страница 22: ...SPECIFICATIONS EATON Powerware BladeUPS Bar Installation Guide S 164201723 Rev P01 18...
Страница 24: ...SERVICE AND SUPPORT EATON Powerware BladeUPS Bar Installation Guide S 164201723 Rev P01 20...
Страница 25: ......
Страница 26: ......
Страница 27: ......
Страница 28: ...164201723P01 164201723 P01...