Eaton Pow-R-Line P1R Series Скачать руководство пользователя страница 9

Instruction Manual 

 

Pow-R-Line Retrofit Panelboards 

Page 

9   

 

 

 

Effective: November 2007 

P1R & P2R Retrofit  Panels 

                                                        

 

For more information visit: www.EatonCanada.ca                

                           11/2007  

TO PREVENT 

DAMAGE TO GROUND FAULT 

CONTROL CIRCUITS, METERING CIRCUITS, OR 
OTHER CONTROL CIRCUITS WHEN 
MEGGERING PANELBOARD, ISOLATE 
CIRCUITS FROM 
PANELBOARD SYSTEM BEFORE BEGINNING 
THE MEGGER OPERATION. BE SURE TO 
RECONNECT THOSE CIRCUITS AFTER 
MEGGER TESTS ARE COMPLETED. NOTE: 
SOME GROUND FAULT CIRCUITS MAY NOT BE 
FUSED, THEREFORE ISOLATION OF THOSE 
CIRCUITS REQUIRES 

DISCONNECTING WIRING FROM BUS BARS. 
 

 

DO NOT USE AC DIELECTRIC/MEGGER 
TESTING. 
 

Energizing Panelboard 

 

Extreme hazards can exist when energizing 
electrical distribution equipment and panelboards. 
Take all precautions necessary to protect people 
and property when energizing the equipment. Short 
circuits and ground faults may exist as a result from 
inadequate installation. Short circuits and ground 
faults within the panelboard can cause catastrophic 
damage, injury and death. 

1.  Determine and always use proper Personnel 

Protective Equipment  (PPE) per NFPA 
70E. 

2.  Prior to energizing the panelboard, turn OFF 

all overcurrent devices and loads internal to 
the panelboard plus mains in downstream 
equipment. 

3.  Verify and follow the sequence of 

energizing circuits and loads. Verify phase 
sequencing on loads, such as motors, which 
can be damaged or destroyed by incorrect 
phase connections. 

4.  If provided, use remote operators to close 

and energize panelboard, overcurrent 
devices and loads. 

5.  Beginning with the main(s), turn ON each 

overcurrent device. 

Maintenance 

It is essential to maintain the equipment in 
satisfactory condition. 
To ensure continued quality service, a systematic 
maintenance schedule is vital. Facility operation and 
local conditions vary to such an extent that the 
schedule must be prepared to suit the conditions. 
The maintenance schedule for individual devices, 
such as circuit breakers, meters, fusible switches, 
etc., should be based upon recommendations 
contained in the individual instruction leaflet for each 

device. Inspection and test operations should be 
coordinated with an overall testing program to result 
in the least operating inconvenience and system 
shutdowns. 

 
Prior to performing any maintenance on the 
panelboard, first de-energize the panelboard at 
the source. Use lockout/ tag-out precautions as 
prescribed in OSHA, NFPA 70E and other safety 
manuals. 
The panelboard should be given a thorough 
maintenance check annually. 
Exercise extreme care to prevent the equipment 
from being connected to the power source while 
tests

 

are being conducted. 

  

IL01417001E

Содержание Pow-R-Line P1R Series

Страница 1: ...els For more information visit www EatonCanada ca Contents INSTALLATION CRITERIA 2 SAFETY MEASURES 3 PRE INSTALLATION RECEIVING HANDLING AND STORAGE 4 REMOVAL OF EXISTING PANELBOARD INTERIOR 4 INSTALL...

Страница 2: ...er BAB 30 60 100 26 5 14 25 4 5 Breaker BAB 42 60 100 33 5 14 25 4 5 Breaker E or F Frame 18 60 225 30 14 25 4 5 Breaker E or F Frame 30 60 225 36 14 25 4 5 Breaker E or F Frame 42 60 225 42 14 25 4 5...

Страница 3: ...ons of this custom built product Eaton Electrical has made all reasonable efforts to ensure that the instructions in this document are adequate and free of material errors and omissions Eaton Electric...

Страница 4: ...SHOULD INSTALL AND OR SERVICE THIS EQUIPMENT Removal of Existing Panelboard Interior DO NOT work on electrical equipment while energized Verify power entering the equipment is de energized at the sou...

Страница 5: ...t compromising wire bending space requirements as listed in the Appendix Table 1 Ensure that electrical clearance requirements are maintained per NECTM CECTM Care must be taken to ensure that the trim...

Страница 6: ...Never clip cable wire strands in order to fit within connectors If cable wire does not match the rating of the connector contact the manufacturer Use an antioxidant compound if required Insert bare c...

Страница 7: ...lly inspect panelboard insulators bus bar and conductors for damage DO NOT ENERGIZE IF DAMAGE IS FOUND Contact Eaton Electrical Circuit Breakers Circuit breakers are typically shipped in either the op...

Страница 8: ...DE ENERGIZED FAILURE TO SHORT OR DISCONNECT DURING PANELBOARD TESTING WILL RESULT IN FAILURE OF ELECTRONIC COMPONENTS DISCONNECT POWER AT SOURCE BEFORE REMOVING OR INSTALLING FUSES HAZARDOUS VOLTAGE...

Страница 9: ...ns in downstream equipment 3 Verify and follow the sequence of energizing circuits and loads Verify phase sequencing on loads such as motors which can be damaged or destroyed by incorrect phase connec...

Страница 10: ...ces metering equipment and other components Damage to insulation and other surface materials can occur Do Not Use Compressed Air in cleaning Maintenance after Cleaning After cleaning perform a second...

Страница 11: ...t a series of inspections be made at quarterly intervals until the progressive effects of local conditions can be analyzed to determine a regular schedule Panelboard Events and Service Interruptions S...

Страница 12: ...rials and tools from the equipment Inspect all connections for damage and torque Re install all covers fillers dead front assemblies and side sheets Conduct panelboard insulation resistance testing de...

Страница 13: ...for Copper or Aluminum Bus Bar Connections Bolt Size Torque Inch Lbs Torque Foot Lbs 10 30 2 5 65 5 4 5 16 130 10 8 3 8 240 20 600 50 National Electrical Code and NEC are registered trademarks of the...

Страница 14: ...P2R Retrofit Panels For more information visit www EatonCanada ca 11 2007 Notes 2007 Eaton Corporation All Rights Reserved Printed in Canada Publication No PUB50895 November 2007 Eaton Yale Company 5...

Отзывы: