Instruction Leaflet IL019107EN
Effective October 2015
Magnum DS
T
switchgear terminal boots
for cable connections—installation
m
WARNING
(1) ONLY QUALIFIED ELECTRICAL PERSONNEL SHOULD
BE PERMITTED TO WORK ON THE EQUIPMENT.
(2) DO NOT ATTEMPT TO INSTALL OR PERFORM
MAINTENANCE ON THE EQUIPMENT WHILE
ENERGIZED. ALWAYS VERIFY THAT NO VOLTAGE
IS PRESENT BEFORE PROCEEDING.
(3) ALWAYS DE-ENERGIZE PRIMARY AND SECONDARY
CIRCUITS IF A CIRCUIT BREAKER CANNOT BE
REMOVED TO A SAFE WORK LOCATION.
(4) DRAWOUT CIRCUIT BREAKERS SHOULD BE LEVERED
[RACKED] OUT TO THE DISCONNECT POSITION.
FAILURE TO FOLLOW THESE STEPS FOR ALL
PROCEDURES DESCRIBED IN THIS INSTRUCTION
LEAFLET COULD RESULT IN DEATH, BODILY INJURY,
OR PROPERTY DAMAGE.
General
Care should be exercised during installation to
minimize cuts and gaps in the boot material for
maximum coverage of the connection.
Required tools and supplies
•
Heavy-duty box cutter knife or similar
•
Plastic cable wire-ties
Parts provided
Each shipment shall contain one terminal boot per
phase for each circuit. Boots vary in size based on
the number of lugs/cables per terminal adapter.
The illustrations herein represent only one size,
but all items are installed in like manner.
Installation of insulated
terminal boots
Step 1
As shown in
Figure 1
, open the “clam-shell”
shaped boot with the “hinge” area away from the
cable path. Flex and install the boot so that the
opening in the boot will surround the conductor
between the glass-polyester conductor support
and the cables. Orient the boot so that the
terminal adapter copper bar will be encased inside.
Figure 1. Step 1