- 5 -
3. Machine Setup and Installation
TAKE CARE TO AVOID DAMAGE TO THE MOTOR AND ASSEMBLY
WHILE LIFTING OR TRANSPORTING THE MACHINE!
3.1 Transportation
Use a fork lift or tow motor to remove the machine from its shipping container or pallet.
3.2 Working Height Adjustment
While elevated, install the adjustable legs onto the machine. Set each leg to the same height to ensure
the machine is level when placed onto the ground.
The working height should be set such that the operator is able to comfortably operate the machine
while maintaining approximately 1/2in (10mm) of distance from the machine.
3.3 Air Line Filter
1.
Connect air source
2.
Adjust regulator to 4-6.5 bars of air pressure
3.
Adjust for proper carton feed speed
4.
Verify emergency switch position
3.4 Carton Supply Shelf
Install the carton supply shelf as depicted.