CONNECTING THE AC LINE VOLTAGE:
Electrically, the Power
II
is wired in series with the incoming AC supply
from the breaker box to the operator. The connector labeled "AC In" is
connected to the main AC supply. The "AC Out" is connected to the
operator.
Connect the incoming AC line to the
AC In
as follows:
L - AC Line In (Live): Black
N - AC neutral (Common): White
G - AC Ground (Earth): Green
Connect the outgoing AC Out line to the Operator as follows:
L - AC Line Out: Black
N - AC neutral: White
G - AC Ground: Green
Refer to the installation manual provided with operator for the
proper connections to the operator
APPLYING THE POWER AND CONNECTING THE SYSTEM RELAY
INSTALLATION OF THE EAGLE POWER-
II
Eagle recommends surge protection be installed on the
incoming 110 AC Line to the battery back-up unit.
IMPORTANT!
(4)
With the power to the operator and breaker box turned off and all of the AC line
connections are complete, install the provided relay. After 5 to 10 seconds the
green inverter light will turn on. Then run the operator with the main breaker off
to test the Power
I
. When testing is completed, turn on the breaker and the green
inverter light will go off, then the charger green or yellow light will go on.
Connect the two orange wires from the sub panel to the "exit open" on the operator.
Using this connection will immediatly open the gate upon power failure. The operator
will resume normal operation when power is resumed.
FOR HOLD OPEN APPLICATION
REMINDER:
There is a time delay of approximately 1-3 seconds between a power
failure and the initial functioning of the Power
II
.