CONNECTING THE AC LINE VOLTAGE:

Electrically, the Power

II

is wired in series with the incoming AC supply

from the breaker box to the operator. The connector labeled "AC In" is
connected to the main AC supply. The "AC Out" is connected to the
operator.

Connect the incoming AC line to the

AC In

as follows:

L - AC Line In (Live): Black
N - AC neutral (Common): White
G - AC Ground (Earth): Green

Connect the outgoing AC Out line to the Operator as follows:

L - AC Line Out: Black
N - AC neutral: White
G - AC Ground: Green

Refer to the installation manual provided with operator for the

proper connections to the operator

APPLYING THE POWER AND CONNECTING THE SYSTEM RELAY

INSTALLATION OF THE EAGLE POWER-

II

Eagle recommends surge protection be installed on the

incoming 110 AC Line to the battery back-up unit.

IMPORTANT!

(4)

With the power to the operator and breaker box turned off and all of the AC line
connections are complete, install the provided relay. After 5 to 10 seconds the
green inverter light will turn on. Then run the operator with the main breaker off
to test the Power

I

. When testing is completed, turn on the breaker and the green

inverter light will go off, then the charger green or yellow light will go on.

Connect the two orange wires from the sub panel to the "exit open" on the operator.
Using this connection will immediatly open the gate upon power failure. The operator
will resume normal operation when power is resumed.

FOR HOLD OPEN APPLICATION

REMINDER:

There is a time delay of approximately 1-3 seconds between a power
failure and the initial functioning of the Power

II

.

Содержание Power II

Страница 1: ...INSTALLATION OWNER S MANUAL INSTALLATION OWNER S MANUAL PHONE 818 764 6690 TOLL FREE 800 708 8848 THE EAGLE POWER II BATTERY BACK UP Control Box Battery Box...

Страница 2: ...the Eagle Power II First and recommended when experiencing a power failure the back up system not only supplies continuous power to run the gate operator but will supply all of the the AC accessories...

Страница 3: ...FIED TECHNICIAN CAUTION THE POWER II IS DESIGNEDTO PROVIDE POWER TO A GATE OPERATOR IN CASE OF A POWER FAILURE OR THE POWER IS SHUT OFF THE OPERATOR CAN START UNEXPECTEDLY WHEN THE AC POWER IS NOT SUP...

Страница 4: ...An extra 70AH battery comes with separate mounting box and cables Weight 65 lbs All ratings are for operators including The Diamond Control Board and three of the following accessories Loop Detector...

Страница 5: ...recommends surge protection be installed on the incoming 110 AC Line to the battery back up unit IMPORTANT 4 With the power to the operator and breaker box turned off and all of the AC line connectio...

Страница 6: ...INSIDE OF THE EAGLE POWER II 5 2000 Watt Inverter Battery Terminals Battery Charger Control Box Control Sub Panel Battery Box 70 Ah Battery AC OUT Hold Open AC IN...

Страница 7: ...EAGLE POWER I 6 Rear View of Control Box 21 10 OC 1 13 3 8 18 1 2 20 OC Mounting Bracket Holes 3 8 Diameter Rear View of Battery Box Mounting Bracket Holes 3 8 Diameter 16 2 1 2 2 1 2 7 1 2 OC 12 1 2...

Страница 8: ...THE EAGLE POWER II 7 Recommended Installation with flex conduit Control Box Battery Box 3 4 Water tight flexible conduit with fittings...

Страница 9: ...ned to E agle for warranty repair within the warranty period which upon receipt by E agle are confirmed to be defective and covered by this limited warranty will be repaired or replaced at E agle s so...

Отзывы: