Eagle A100 Скачать руководство пользователя страница 3

3

Introduction

This  instruction  manual  is  intended  to  assist  those  involved 

with  the  installation,  operation  and  maintenance  of  Eagle 

Model A100 pumps. It is recommended that this manual be 

thoroughly reviewed prior to installing or performing any work 

on the pump or motor.

I-A. Importance of Instructions

The  design,  material  and  workmanship  incorporated  in  the 

construction  of  Eagle  pumps  make  them  capable  of  giving 

long, trouble–free service. The life and satisfactory service of 

any mechanical unit, however, is enhanced and extended by 

periodic inspection and careful maintenance. This instruction 

manual was prepared to assist operators in understanding the 

construction and correct methods of installing, operating, and 

maintaining these pumps.

Study  thoroughly  Sections  I,  II,  III,  and  carefully  follow  the 

instructions for installation and operation. Sections IV, V, VI, 

VII, and VIII are answers to trouble and maintenance questions. 

Keep this instruction manual handy for reference.

I-B. Special Warnings

Eagle Pump and Compressor will not be liable for any damages 

or delay caused by failure to comply with the provisions of this 

instruction manual. This pump is not to be operated at speeds, 

working pressures, discharge pressures, or temperatures higher 

than nor used with liquids other than originally intended for, 

without written permission of Eagle Pump.

I-C. Receiving Inspection—Shortages

Care should be taken when unloading pumps. If shipment is 

not delivered in good order and in accordance with the Bill–of–

Lading, note the damage or shortage on both receipt and freight 

bill. MAKE ANY CLAIMS TO THE TRANSPORTATION 

COMPANY PROMPTLY. 

SECTION I—GENERAL

Instruction  sheets  on  various  components  as  well  as  the 

Instruction Book for the pump are included in the shipment. 

DO NOT DISCARD! 

I-D. Preservation and Storage 

Eagle’s  normal  domestic  shipping  and  storage  preparation  is 

suitable for protecting the pump during shipment in covered 

trucks. It also provides protection during covered storage at the 

jobsite, and for a short period between installation and start-up. 

If  the  pump  is  to  be  idle  and  exposed  to  the  elements  for 

an extended period, either before or after installation, special 

precautions are required. One approach is to provide special 

preservatives  and  wrapping  before  shipment.  However,  after 

installation the protective wrappings will have been removed. 

Therefore,  application  of  preservatives  after  installation  is 

considered a good practice. 

The driver, coupling, and mechanical seal manufacturers should 

be contacted for their recommendations on preservation and 

protection procedures.

I-E. Handling Techniques

Care should be used in moving pumps. Pumps should not be 

hoisted by eyebolts. These eyebolts are intended for removing 

the back pull–out assembly for maintenance and inspection. An 

assembled pump should be hoisted using a sling under suction 

flange and under rear of bearing frame. Bedplate mounted units 

should be hoisted using slings under bedplate below both pump 

and driver.

II-A. Location

Pumping  unit  should  be  placed  as  close  as  practical  to  the 

source of supply. Floor space and headroom allotted to the unit 

must be sufficient for inspection and maintenance. Be sure to 

allow for crane or hoist service.

II-B. Foundations

1. 

Grouted

—Bedplate mounted units are normally grouted–in 

on a concrete foundation, which has been poured on a solid 

footing. This allows a permanent, vibration–absorbing base for 

the unit. The location and size of foundation bolts are shown 

on the outline assembly drawings supplied for the unit. Fig. 1 

illustrates a typical foundation bolt installation.

2. 

Flexibly Mounted

—Installation and leveling of the optional 

flexibly mounted bedplate should be carried out in accordance 

with  assembly  drawings  supplied  in  the  data  package  for  the 

unit.

SECTION  II—INSTALLATION

Figure  1

LEAVE 3/4" TO11/2" UNDER 

BEDPLATE FOR GROUT

WEDGES

DAM

WASTE

BEDPLATE

GROUT

LEAVE TOP OF

FOUNDATION ROUGH,

AND WET BEFORE

GROUTING.

CONCRETE 

FOUNDATION

Содержание A100

Страница 1: ...EAGLE Installation Operation and Maintenance Instructions EAGLE MODEL A100 ANSI PUMPS Lubrication information is in Section III A Item 1b and Section IV A...

Страница 2: ...III B Operation Checks 6 III C Shutdown Procedure 6 SECTION IV PREVENTIVE AND CORRECTIVE MAINTENANCE IV A Lubrication 6 IV B Stuffing Box 6 IV C Vibration 6 IV D Alignment Final 6 IV E Performance 6...

Страница 3: ...r protecting the pump during shipment in covered trucks It also provides protection during covered storage at the jobsite and for a short period between installation and start up If the pump is to be...

Страница 4: ...shipped with bedplates Changing the pump casing or bearing frame in the field will require a reshimming of the frame foot The proper number of shims is installed when the pump shaft is level and para...

Страница 5: ...ng connection also refer to packing recommendations 2 Mechanical Seals When mechanical seals are supplied they are installed and adjusted at the factory They must not run dry or in abrasives Connect r...

Страница 6: ...turer Check complete unit for excessive vibration and unusual noises Do not run pump at greatly reduced flow because damage can result III C Shutdown Procedure Back flow through pump will cause revers...

Страница 7: ...e cover off shaft Do not damage oil seal 332A Slide bearing housing off shaft o Straighten tang in lock washer and remove bearing locknut 136 and lock washer 382 Remove ball bearing 112A using a beari...

Страница 8: ...of the stuffing box 2 Remove the impeller and stuffing box 3 Assemble the gland 250 with gaskets and stationary seat and slide the assembly over the shaft 122 or shaft sleeve 126 4 Slide the rotary p...

Страница 9: ...om casing Tighten bolts 370C and jam nuts on bolts 370D e If desired a dial indicator can be used instead of a feeler gauge to check that the bearing housing has been moved the correct distance V D Ad...

Страница 10: ...TERIAL Part Name No Reqd Per Pump Parts List and Materials of Construction 1 1 1 1 Set 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 4 1 1 4 24 3 4 3 4 2 1 2 2 6 1 1 2 3 2 1 1 1 1 Casing Impelle...

Страница 11: ...11 Model A100 S M L Assembly View of 8 Pumps Only 100 239 105 106 412A 469D 101 351 122A 355 353 107 333A 370D 113A 496 361A 168A 123 210 261 126 370H 184 370 228A 112A 134A 332A 136 382 370C 370 503...

Страница 12: ...12 Model A100 M L 132 370 184 168A 360D 496 108 107 355 353 123 113A 228A 370C 134A 136 382 332A 112A 370D 361A 370E 370H 126 122A 210 333A 106 370F 131 239 105 469D 412A 106 101 351 100...

Страница 13: ...13 Model A100 X 101 412A 469D 106 105 184 351 100 370H 239 355 107 370 370E 131 228A 370F 106 333A 469B 353 113A 168A 123 261 126 108 210 132 122A 360D 370D 371C 109A 332A 136 382 496A 134A 112A 496...

Страница 14: ...as required 17 Coupling or pump and driver misaligned check alignment and realign if required 18 Impeller diameter too small consult factory for proper impeller diameter 19 Improper pressure gauge loc...

Страница 15: ...ing instructions VIII A Spare Parts To insure against possible long and costly downtime periods especially on critical services it is advisable to have spare parts on hand 1 For critical services It i...

Страница 16: ...MP COMPRESSOR LTD 7025 5 Street S E Calgary AB T2H 2G2 Canada ANSI Centrifugal Pumps Multistage Horizontal Pumps Vertical Sump Pumps Rotary Screw Compressor Air Gas Dryers www eagle pc com Printed in...

Отзывы: