INSTALLATION
INSTALLATION PREPERATION
A. 1 Check the floor area where the tub is to be installed.
B. A Clean the area of any debris or trash.
C. B Use a 5 or 6-foot level and determine if the floor is level. If the floor is not level, adjust all 4
leveling feet to perfectly level the tub. Note: it is important that ALL leveling feet are
completely touching the floor and level for the door system to work properly.
D. 2 Check to insure the drain rough has been placed at the proper location. See spec sheets
attached for you unit.
E. 3 Insure that the proper electrical service has been installed at the pump location. See
electrical requirements below.
ELECTRICAL REQUIREMENTS
A. Equipment utilized on these baths requires individual dedicated service for each feature
unless otherwise stated on the actual product.
B. Each electrical service must be a dedicated 20 amp, 110-125 volts alternating current
service that is GFCI protected.
a. Hydro Jet Massage Systems require one 15 amp, 110 volt service that is GFCI
protected.
b. Hydro Air-Massage Systems require one 15 amp, 110 volt service that is GFCI
protected.
c. Dual Massage Systems require two dedicated electrical circuits: 20 amps, 110 volt,
GFCI for the pump and blower.
* IN-LINE HEATER WILL ALWAYS REQUIRE ITS OWN DEDICATED 20 AMP, 110 VOLT GFCI
PROTECTED CIRCUIT.
ELECTRICAL INSTALLATION