7)  Installation Requirements 

 

7.1.  Installation Standards Compliance 

 

 

Warning – High voltage may be 
present, risk of electric shock. 
DO NOT open when energised, 
disconnect power before opening. 

 
The  beacon  must  only  be  installed  by  suitably  qualified 
personnel in accordance with the latest issues of the relevant 
standards. 
 

ATEX / IECEx & UKEx installation standards 

 

EN60079-14  /  IEC60079-14:  Explosive  atmospheres  -  
Electrical installations design, selection and erection.

 

 

EN60079-10-1 / IEC60079-10-1: Explosive atmospheres 
- Classification of areas. Explosive gas atmospheres.

 

 

EN60079-10-2 / IEC60079-10-2: Explosive atmospheres 
- Classification of areas. Explosive dust atmospheres. 
 
The installation of the units must also be in accordance 
with any local codes that may apply and should only be 
carried out by a competent electrical engineer who has 
the necessary training. 
 
NEC / CEC Installation Standards 

 

Cautions 

 

Attention:  Installation  must  be  carried  out  by  an
electrician  in  compliance  with  the  National  Electrical
Code, NFPA 70 or CSA 22.1 Canadian Electrical Code,
Part  I,  Safety  Standard  for  Electrical  Installations,
Section  32.  /  L'installation  doit  exclusivement  être 
réalisée  par  du  personnel  qualifié,  conformément  au
code national d'électricité américain, NFPA 70 ou CSA
22.1  Code  canadien  de  l'électricité,  première  partie,
norme de sécurité relative aux installations électriques,
Section 32. 

 

Attention:  Disconnect  from  power  source  before
installation  or  service  to  prevent  electric  shock  /
Débranchez-le  de  la  source  d'alimentation  avant
l'installation  ou  l'entretien  pour  éviter  tout  choc
électrique. 
 
The installation of the units must also be in accordance 
with any local codes that may apply and should only be 
carried out by a competent electrical engineer who has 
the necessary training. 

 

7.2. Cable Selection and Connections 

 
When selecting the cable size, consideration must be given to 
the input current that each unit draws (see table 1), the number 
of beacons on the line and the length of the cable runs. The 
cable  size  selected  must  have  the  necessary  capacity  to 
provide the input current to all of the beacons connected to the 
line.  
 
Electrical connections are to be made into the terminal blocks 
on  the  PCBA,  using  solid  wire  0.5-4mm2  /  AWG  20-12  or 
stranded wire, sizes 0.5-2.5mm2 / AWG 24-14. Wire insulation 
needs to be stripped 8mm. Wires may be fitted securely with 
crimped ferrules. 
 

 

Figure 4: Wire Preparation.

 

 
Terminal screws need to be tightened down with a tightening 
torque of 0.45 Nm / 5 Lb-in. A 5-way terminal block is provided 
on  the  AC  Beacon:  2-off  Live,  2-off  Neutral  and  1-off  Earth 
terminals in total. A 4-way terminal block is provided on the DC 
Beacon: 2-off +ve and 2-off -ve terminals. 

 

Figure 5: STExB2 Entries and Terminal Block Location.

 

 
When connecting wires to the terminals great care should be 
taken to dress the wires so that when the cover is inserted into 
the  chamber  the  wires  do  not  exert  excess  pressure  on  the 
terminal  blocks.  This  is  particularly  important  when  using 
cables with large cross-sectional areas such as 2.5mm². 
 

Earthing 

 
Please note that for AC supply voltage product versions the 
Earth terminal on the PCBA does not provide an earth 
connection to the product enclosure. The enclosure must be 
independently earthed using either the external or internal 
earth fixing point, (see fig 9 and notes below). 
 
Internal earthing connections should be made to the Internal 
Earth terminal in the base of the housing using a ring crimp 
terminal to secure the earth conductor under the earth clamp. 
The earth conductor should be at least equal in size and rating 
to the incoming power conductors. 
 
External earthing connections should be made to the M5 earth 
stud, using a ring crimp terminal to secure the earth conductor 
to the earth stud. The external earth conductor should be at 
least 4mm2 in size. 
 
 
 
 
 
 
 
 
 
 

Содержание STExB2X05

Страница 1: ...4Vdc 145mA 150mA STExB2X05AC115 115Vac 110 120Vac 50 60Hz 140mA 200mA STExB2X05AC230 230Vac 220 240Vac 50 60Hz 70mA 100mA STExB2X10DC024 24Vdc 20 28Vdc 605mA 710mA STExB2X10DC048 48Vdc 42 54Vdc 230mA...

Страница 2: ...C Db Ta 50 C to 70 C STExB2 X10AC115 X10AC230 Ex db IIC T4 Gb Ta 50 C to 70 C Ex tb IIIC T128 C Db Ta 50 C to 70 C STExB2 X15DC024 X15DC048 Ex db IIC T4 Gb Ta 50 C to 70 C Ex tb IIIC T127 C Db Ta 55...

Страница 3: ...Suitable The certification approval has validated continuous use up to 38 C ambient and are for transient use up to 70 C ambient Installation must be carried out in compliance with the National Elect...

Страница 4: ...unit STExB2X21 models shall not be mounted with the lamp down The STEx beacons should be securely bolted to a flat surface using 9 0mm diameter bolt holes in the base of the unit See figure 2 Figure...

Страница 5: ...rical engineer who has the necessary training 7 2 Cable Selection and Connections When selecting the cable size consideration must be given to the input current that each unit draws see table 1 the nu...

Страница 6: ...certified blanking plugs NEC CEC Requirements Only The cable entries have an M20 x 1 5 6H entry thread If the installation is made using cable glands only suitably rated and certified cable glands mu...

Страница 7: ...a minimum resistance value of 3k3 ohms and a minimum wattage of 0 5W or a minimum resistance value of 500 ohms and a minimum wattage of 2W The resistor must be connected directly across the ve and ve...

Страница 8: ...nd any dust layer removed prior to opening the unit Repair of the flameproof threaded joints and cemented joints is not permitted Potential electrostatic charging hazard Clean only with a damp cloth 1...

Страница 9: ...Page left Intentionally blank...

Страница 10: ...R DIMENSIONAL TOLS STANDARDS MOD No REASON INITIAL DATE ISSUE DATE APPROVED CHECKED DATE DATE DRAWN WEIGHT Kg SURFACE FINISH MATERIAL ALTERNATIVE MATERIAL SHEET SCALE TITLE A3 IF IN DOUBT ASK DO NOT S...

Страница 11: ...NGULAR DIMENSIONAL TOLS STANDARDS MOD No REASON INITIAL DATE ISSUE DATE APPROVED CHECKED DATE DATE DRAWN WEIGHT Kg SURFACE FINISH MATERIAL ALTERNATIVE MATERIAL SHEET SCALE TITLE A3 IF IN DOUBT ASK DO...

Страница 12: ...Netherlands B V Utrechtseweg 310 6812 AR Arnhem Netherlands Quality Assurance Notification Module D SIRA 05 ATEX M342 Provisions fulfilled by the equipment II 2G Ex db IIC T6 T3 Gb II 2D Ex tb IIIC T...

Страница 13: ...e and Place of Issue London 03 12 2021 EU Declaration of Conformity On behalf of European Safety Systems Ltd I declare that on the date the equipment accompanied by this declaration is placed on the m...

Страница 14: ...0518 Rake Lane Eccleston Chester CH4 9JN UK Quality Assurance Notification Module D CSAE 22UKQAN0046 Provisions fulfilled by the equipment II 2G Ex db IIC T6 T3 Gb II 2D Ex tb IIIC T85 C T137 C Db IP6...

Страница 15: ...nd Place of Issue London 24 02 2022 UKCA Declaration of Conformity On behalf of European Safety Systems Ltd I declare that on the date the equipment accompanied by this declaration is placed on the ma...

Страница 16: ...Page left Intentionally blank...

Отзывы: