30
CAUTION
WHAT TO DO IF YOU SMELL GAS
• Do not try to light any appliance.
• Do not touch any electrical switch; do not use any
phone in your building.
• Immediately call your gas supplier from a
neighbor’s phone. Follow gas supplier’s
instructions.
•
If you cannot reach your gas supplier, call the fire
department.
!
NOTICE
Use of CSA approved corrugated, semi-rigid stainless
steel tubing with polyethylene jacketing is approved
for use with boilers following tubing manufacturer's
instructions.
Use of flexible
"appliance whip" gas tubing is not
allowed per NFPA 54.
WARNING
Fire, explosion, asphyxiation and burn hazard. Boiler
piping and gas connections shall be leak tested before
placing boiler in operation. Failure to follow these
instructions and or improper installation could result in
death or serious injury.
!
Required Gas Supply Pressure
Natural Gas
Liquid Propane
Min.
Max.
Min.
Max.
3.5" w.c. 10.5" w.c.
8.0" w.c.
13.0" w.c.
(0.87 kPa) (2.61 kPa)
(1.99 kPa)
(3.23 kPa)
Gas Supply Required
Model
Natural Gas (A)
Liquid Propane (E)
DCBF-125 118 ft
3/h (
3.30
m3/h)
51 ft
3/h (
1.48
m3/h)
DCCF-150 143 ft
3
/h (4.00 m
3
/h) 61.15 ft
3
/h (1.72 m
3
/h)
DANGER
Fire Hazard. Do not use matches, candles, open
flames, or other methods providing ignition source.
Failure to comply will result in death or serious injury.
!
WARNING
If overheating occurs or gas supply fails to shut off, do
not turn off or disconnect the electrical supply to the
pump. Shut off gas supply at a location external to the
appliance.
Do not use this boiler if any part has been under
water. Call a qualified service technician before use.
!
7 - GAS SUPPLY PIPING
NOTICE
If overheating occurs or gas supply fails to shut off, do
not turn off or disconnect electrical supply to pump.
Shut off gas supply at location external to the boiler.
• Boiler shall be isolated from the gas supply piping
system by closing its individual manual shutoff valve
during any pressure testing of gas supply piping
system at test pressures equal to or less than 1/2 psi
(3.5 kPa).
• Install boiler so that gas ignition system components
are protected from water (dripping, spraying,rain,
etc.) during appliance operation and service
(circulator replacement, condensate trap, control
replacement, etc.).
• Gas meter and supply pipes must be capable of delivering
the listed quantity of gas in addition to demand from
any other appliances in the house. Boiler requires a 3/4”
(19.5 mm) gas supply pipe.
• Support piping with hooks straps, bands, brackets,
hangers, or building structure components to prevent or
dampen excessive vibrations and prevent strain on gas
connection. Boiler will not support piping weight.
• Use thread (joint) compound (pipe dope) suitable for
liquefied petroleum gas.
•
Install external field sourced manual main gas shutoff
valve, ground joint union, and sediment trap upstream of
gas controls. See Figure 7-1.
• Install boiler so gas ignition system components are
protected from water dripping, spraying,rain, etc. During
appliance operation and service.
• Leak test boiler and gas line connections before placing
boiler into operation.
7.1 General
• Use piping materials and joining methods acceptable
to authority having jurisdiction. In absence of such
requirements:
• USA - National Fuel Gas Code, ANSI Z223.1/NFPA 54
•
Install manual main shutoff valve before the gas valve
accordance with state and local requirements.
•
Size and install gas piping system to provide sufficient gas
supply to meet maximum input at not less than minimum
supply pressure.
•
Boiler and its individual shutoff valve shall be disconnected
from gas supply piping system during any pressure testing
of that system at test pressures in excess of 1/2 psi (3.40
kPa - 34.47 mbar).
240012564 REV A, [05/15/2019]