3.0 INSTALLATION
3.5 DUCT CONNECTIONS
All ducts shall be made according to local and/
or national codes and also with good duct
installation practice. Minimize static losses by
limiting the number of bends.
Suspended duct work with flexible hangers
shall not be fastened directly to the unit.
A length of straight duct shall be installed as
per Figure 3.5. This is to ensure uniform flow
of discharge air. If an elbow need to be
installed, then it shall be 1.5 of equivalent duct
diameter. (Equivalent duct Ø= (4ab/
π
)
0.5
).
Please refer to AMCA standard for proper
ducting installation/ guidelines.
FIGURE 3.5: SUGGESTED METHOD FOR CONNECTING SUPPLY DUCT
Model A
R
HEB/EB 68D – 125D
40”[1016mm] 25”[635mm]
HEB/EB 160D – 760D
60”[1524mm] 35”[889mm]
EB 800D – 1520D
80”[2032mm] 50”[1270mm]
Note: Transition element shall not be greater than 15° for converging elements nor greater 7° for diverging element.
3.6 FIELD PIPING
1.) COMPRESSOR (CONDENSING UNIT) IS ABOVE THE EVAPORATING UNIT.
Note: Traps should be provided for every 20 ft [6.1m] of vertical riser for proper oil movement.
11
Содержание MM0305F
Страница 7: ...3 0 INSTALLATION ACCS 480 510 570 ACCS 640 700 760 ACCS 800 890 960 ACCS 1020 1140 1340 1520 7 ...
Страница 24: ...4 0 OPERATION 4 10 TYPICAL OPERATING SEQUENCE 24 ...
Страница 26: ...5 0 MAINTENANCE 5 2 TROUBLE SHOOTING CHART 26 ...
Страница 27: ...5 0 MAINTENANCE 27 ...
Страница 28: ...5 0 MAINTENANCE 28 ...