page 9 of 28
Foundation
™
for LED Panels
Section 3.2 - For LED arrays 7 panels or higher - 3 Horizontal Rails
1. Mark the location of the Bottom Left Corner of the viewing area.
2. Measure up 19.8”
(489mm)
and draw a level horizontal line equal to the width of the LED Wall.
This is the location of the bottom rail mounting points.
3. Measure up 34.2”
(869mm)
from the first line and draw a horizontal line parallel to the first line and the floor.
4. Measure up 53.8”
(1367mm)
from the second line and draw a horizontal line parallel to the first lines and the
floor.
5A. If installing onto a Drywall/Gypsum Board surface, locate the wall studs and mark their location at the
intersection of the lines drawn in steps 2 & 3. These are mounting locations for the wall brackets.
5B.
If installing into brick or block wall, evenly space the vertical lines no more than 32”
(813mm)
apart.
6.
Loosely attach the wall mounting hardware
(provided by others)
to the wall at the outer four corners of the grid
created in steps 1-5B. Ensure the head of the hardware is at least
1
/
2
”
(12mm)
off the surface of the wall.
BOTTOM
LEFT OF
VEIWING
AREA
5B
W
ALL
SIDE
VIEW
53.835”
(1367mm)
34.2”
(869mm)
BOTTOM
of Viewing Area
19.8”
(489mm)
4
3
2
1
6
STUD
WALL
Mounting
Hardwar
e
(by others)
5A
Stud locations and
Horizontal Rail positions shown
HORIZONTAL RAIL
PLACEMENT
STUD
TOP
KEYHOLE
The assembled Horizontal Rails will be hung from
these in SECTION 5 - Hanging Horizontal Rails.
Please Note:
It is the responsibility of the installer to
select mounting hardware appropriate
for the mounting surface