B. Assemble mounting plate. Attach 4, 5/8" nuts 2 1/4" from top
of anchor bolts. Set template on bolts. Place 4 more 5/8" nuts
on top of template. Position anchor bolts as illustrated in Figure 2.
C. Pour concrete into the hole 18" from the top. Place four rebars
8" apart forming a square in the center of hole as illustrated in
Figure 1.
D. Finish pouring concrete into hole. Release air pockets in concrete.
E. Drop anchor bolts into the center of the wet concrete until
template is flush with cement. Level mounting plate and make
sure it's parallel with playing surface. Add 4, 5/8" flat washers on
top of nuts. Clean off any excess cement on mounting plate at
this time.
NOTE: Check leveling of mounting plate several times while
concrete is curing. Front of mounting plate must be parallel with
playing surface
Optional Super-Six Surface Mount Installation
A. Ensure ground is level
with playing surface.
Dig hole 16" wide and
48" deep.
F. Remove basketball pole from box and place post
cap on the TOP of the pole.
G. Place basketball pole onto the bolts, add
4 5/8" flatwashers on top of base plate, then
the 4 nylon lock nuts.
H. Use level to check for proper vertical
alignment, then tighten nylon lock nuts.
NOTE: Nuts at the top of assembly are used
for leveling the system after fully assembled.
5/8" nuts
anchor bolts
anchor
template
2 1/4" from top
5/8" flat washers
Figure 2: Anchor Plate Assembly
IMPORTANT! Do Not proceed to Step F until concrete has cured.
A minimum of 72 hours. Allow additional time for cold, wet, or
humid weather.
WARNING! Two person minumum required for Step F .
Not following this warning may resullt in an injury
and/or property damage.
Playing Surface
(Concrete Pad)
1-3”
Anchor System Option:
As an installation option, you can install the
anchor system up to 3” lower than your
playing surface. This allows an area to hide
the anchor bolts with rock, gravel or mulch.
5/8" flat washer
nylon lock nut
Figure 4:
Pole Placement
16"
Playing Surface
Ground Surface
Figure 1: Concrete Footing
48"
18"
Rebar
8"
Minimum 20”
Note: To increase
footing stability,
bell out bottom
of footing.