Installation, Operation and Maintenance manual
9
PowerCore
®
Dust Collectors - Series CPC
Angle not
to exceed 30°
from vertical
Do not lift
with this orientation
30°
Figure 2: Four-point lifting arrangement (CPC-6R and CPV-6FR illustrated)
CPC-3 and CPC-4 assembly
Refer also to figures 2, 3 and 4.
1. Assemble support by attaching cross bracing to legs using hardware supplied.
Do not tighten hardware at this stage.
All bracing require fitting.
2. Lift support assembly into required position and ensure assembly is level.
3. Drill through base holes and insert suitable foundation bolts (if required, details
of foundation fixing positions are provided in Publication 3021).
Foundation bolts are not supplied by Donaldson.
4. Tighten foundation bolts, legs and cross bracing.
5. Stand hopper on the discharge end and apply sealant to top flange, each side of
hole pattern.
6. Following the general guidance to lifting, lift the collector onto hopper. Align
bolt holes in flanges with drift pins, install bolts, washers and nuts and tighten
all round to form an airtight seal.
7. Lift and position the collector and hopper assembly onto support. Align bolt holes
in hopper gussets/legs with drift pins, install bolts, washers and nuts and tighten.
When the collector is fitted with an earthing post, an earthing connection
must be made between the collector side panel and the hopper, using
the earthing cable provided (refer to figure 5).