![Donaldson Torit WSO 25-4 Скачать руководство пользователя страница 18](http://html1.mh-extra.com/html/donaldson-torit/wso-25-4/wso-25-4_installation-and-operation-manual_2520681018.webp)
Donaldson Company, Inc.
15
Electrical installation, service, or maintenance work must be performed by a qualified electrician and comply with all
applicable national and local codes.
This equipment may start or stop unexpectedly from a remote location.
Turn power off and lock out all power before performing service or maintenance work.
The appropriate wiring schematic and electrical rating must be used. See collector’s rating plate for required voltage.
Do not install in classified hazardous atmospheres without an enclosure rated for the application.
Electrical Wiring
Support Installation
Anchors must comply with local code requirements and be capable of supporting dead, live, wind, seismic and other
applicable loads.
Anchor sizes shown are provisional, as final anchor sizing will depend on jobsite load conditions, equipment location,
foundation/framing design variables and local codes.
Consult a qualified engineer for final selection of suitable anchors.
Reference typical leg assembly drawing shipped with the collector prior to starting assembly.
Prepare the foundation or support framing in the selected location. Locate and install anchors.
Lifting Information
Failure to lift the equipment or sub-assemblies correctly can result in severe personal injury and/or property damage.
Only qualified crane or forklift operators should be allowed to lift equipment.
1. Use all lifting points provided.
2. Use clevis connectors, not hooks, on lifting slings.
3. Use spreader bars to prevent damage to equipment.
4.
Check the Specification Control drawing for weight and dimensions of the collector and components to ensure adequate crane
capacity.
5. Lift collector and accessories separately and assemble after collector is in place.
6.
Use drift pins to align holes in section flanges during assembly.