Dometic 600312.321 Скачать руководство пользователя страница 9

9

(Roof Mount Assembly & Wiring Continued on Page 10)

7.

SYSTEM CHECKOUT &
CONFIGURATION

Now that the system is installed, it is necessary to check all
operations and then configure the electronics.

E. ELECTRONIC CONTROL KIT

CONFIGURATION

1)

Adjust the dip switches visible in the Electronic
Control Kit
 according to the options that are
installed. (See FIG. 14). Placing the switch in the
ON position selects that option.
NOTE: Dip switches are shipped from the factory
in the "OFF" position.

2)

Selection of ZONE 2 identifies this unit as Zone 2;
likewise, Zone 3 and 4.

3)

STAGE is not used on these units. Leave in the
"OFF" position.

4)

HEAT STRIP is placed to "ON" if an Electric Heat
Strip is installed.

5)

Replace the junction box cover on the Electronic
Control Kit
.

Refer to the Operating manual for a description of the air
conditioner operation.

6)

SYSTEM CHECKOUT: Verify that all features of
the installed system work. Check fan speeds,
cooling mode, heat pump mode, furnace (if con-
nected) and heat strip. If the features do not work,
check all wiring and confirm that the correct op-
tions have been selected on the Electronic Control
Box. See Comfort Control Center™ Operating
Instructions.

FIG. 15

CELING T EMPLATE

AIR BOX

FIG. 16

CEILING TEMPLATE

AIR BOX

FIG. 14

7)

SYSTEM CONFIGURATION: If all features are
functioning, perform the following configuration
procedure:
a) Simultaneously depress UP and DN

pushbuttons on the Comfort Control Center
for one second. This completes the system
configuration.

8.

AIR BOX INSTALLATION

A. Remove the two filter-grilles from the air box.
B. Slide the air box over the ceiling template.

C. Install the four (4) sharp pointed screws through the air

box legs and into the prepunched holes in ceiling
template. NOTE: There are four optional mounting
holes on the outer edge of the return air opening for
which no screws are provided. These are only required
where an uneven ceiling does not allow proper fitting of
the air box.

D. Install the filter-grilles by pushing them into place.

Содержание 600312.321

Страница 1: ...So Poplar St LaGrange IN 46761 219 463 4858 CANADA Dometic Dist 866 Langs Dr Cambridge Ontario CANADA N3H 2N7 519 653 4390 Form No 3106529 005 6 95 1995 The Dometic Corp LaGrange IN 46761 ROOF TOP AI...

Страница 2: ...air condi tioner is in operation will minimize condensed moisture on cold surfaces 2 PRECAUTIONS DANGER IMPROPER INSTALLATION MAY DAMAGE EQUIP MENT COULD ENDANGER LIFE CAUSE SERIOUS INJURY AND OR PRO...

Страница 3: ...the following before calling your service center A If RV is connected to motor generator check to be sure motor generator is running and producing power B If RV is connected to power supply by a land...

Страница 4: ...oof reinforcing members 2 Mark a 14 1 4 x 14 1 4 square on the roof and carefully cut the opening 3 Using the roof opening as a guide cut the match ing hole in the ceiling D OPENING PREPARATION 1 The...

Страница 5: ...tion into the 14 1 4 roof opening Make sure that at least 15 of the wire extends into the roof opening and 6 extend from the wall at the mounting position of the Comfort Control Center 9 In the event...

Страница 6: ...ble through the hole in the base plate and mount the plate to the wall with the two screws provided Check the alignment to en sure level installation 3 Install the control cable RJ 11 connector into t...

Страница 7: ...the return air opening and pull the conduit power cable down for later connection Pull the low voltage wire and telephone cable down for later connection FIG 8 FIG 10 MEASURE CEILING THICKNESS GASKET...

Страница 8: ...the Electronic Control Kit The polarity of these connections does not matter 4 Connect the previously run Energy Management System wires if applicable to the yellow wires protruding from the Electroni...

Страница 9: ...stem work Check fan speeds cooling mode heat pump mode furnace if con nected and heat strip If the features do not work check all wiring and confirm that the correct op tions have been selected on the...

Страница 10: ...WER DISCHARGE AIR DUCT Attached to Ceiling Template POWER SUPPLY LINE FRAMING RETURN AIR DUCT ROOF REINFORCEMENT MEMBER UPPER DISCHARGE AIR DUCT WALL THERMOSTAT CABLE ROOF LINE DISCHARGE AIR RATING PL...

Страница 11: ...11 WIRING DIAGRAMS AIR CONDITIONER ELECTRONIC CONTROL KIT HEAT PUMP...

Отзывы: