7

7 Start-UP

7.1

General Information

To ensure that start-up is performed correctly, it should only be
carried out by an after-sales service technician authorised by the
manufacturer. This may be a condition for extending the guaran-
tee (see Warranty Service). Start-up should be carried out in
heating operation.

7.2

Preparation

The following items need to be checked prior to start-up:

„

All of the heat pump connections must be established as de-
scribed in Chapter 6.

„

All valves that could impair the proper flow of the heating
water in the heating circuit must be open.

„

The air intake and air outlet paths must be clear.

„

The ventilator must turn in the direction indicated by the ar-
row.

„

The heat pump controller must be adapted to the heating
system in accordance with the controller's operating instruc-
tions.

„

Ensure the condensate outflow functions.

„

The outflow from the heating water pressure relief valve
must also function correctly.

„

De-aeration of the heating system:
Ensure that all heating circuits are open and the heat circu-
lating pump is operating (level III).
Connect the voltage to the heat pump controller. Select the
heat generator 2 operating mode and de-aerate the system
at its highest point. Top up with water if required (maintain
static minimum pressure).

7.3

Start-Up Procedure

The heat pump is started up via the heat pump controller. Adjust-
ments should be made in compliance with the instructions.

The performance level of the circulating pump must be adapted
to the respective heating system. 

The overflow valve must be adjusted to the requirements of the
respective heating system. Incorrect adjustment can lead to
faulty operation and increased energy consumption. We recom-
mend carrying out the following procedure to correctly adjust the
overflow valve:

Close all of the heating circuits that may also be closed during
operation (depending on the type of heat pump usage) so that
the most unfavourable operating state - with respect to the water
flow rate - is achieved. This normally means the heating circuits
of the rooms on the south and west sides of the building. At least
one heating circuit must remain open (e.g. bathroom).

The overflow valve should be opened far enough to produce the
maximum temperature spread between the heating flow and re-
turn flow listed in the following table for the current heat source
temperature. The temperature spread should be measured as
close as possible to the heat pump. The heating element of mono
energy systems should be disconnected.

Any faults occurring during operation are also displayed on the
heat pump controller and can be corrected as described in the
operating instructions of the heat pump controller.

For external temperatures below 10 °C and heating  water tem-
peratures below 16 °C, the buffer tank should be heated up with
the 2nd heat generator to at least 25 °C. 

Observe the following procedure to implement a smooth start-up:

1)

Close all of the heating circuits.

2)

Fully open the overflow valve. 

3)

Use the controller to select the automatic operating mode.

4)

Wait until the buffer tank has reached a temperature of at
least 25 °C. 

5)

Now slowly reopen the heating circuit valves in succession
so that the heating water throughput is constantly raised by
slightly opening the respective heating circuit. The heating
water temperature in the buffer tank must not be allowed to
drop below 20 °C during this process. This ensures  that the
heat pump can be defrosted at any time.

6)

Set the minimum volume flow quantity on the overflow valve
and heat circulating pump when all heating circuits are fully
open and a heating water temperature in the buffer tank of
approx. 20 °C is maintained.

7)

New buildings have an increased heat consumption on ac-
count of the energy required to dry them out. This increased
heat consumption means that marginally dimensioned heat-
ing systems can not always achieve the desired room tem-
perature. In such cases, we recommend keeping a 2nd heat
generator on standby during the first heating period. The
limit temperature on the heat pump controller should also be
turned up to 15 °C.

Heat source
temperature

Max. temperature spread

between heating flow and return 

flow

From

To

-20 °C

-15 °C

4 K

-14 °C

-10 °C

5 K

-9 °C

-5 °C

6 K

-4 °C

0 °C

7 K

1 °C

5 °C

8 K

6 °C

10 °C

9 K

11 °C

15 °C

10 K

16 °C

20 °C

11 K

21 °C

25 °C

12 K

26 °C

30 °C

13 K

31 °C

35 °C

14 K

Содержание LIK 8MER

Страница 1: ...at Pump for Indoor Installation Pompe à chaleur air eau réversible pour installation intérieure Montage und Gebrauchsanweisung Deutsch English Français Instructions d installation et d utilisation Installation and Operating Instructions Bestell Nr Order no No de commande 452160 66 23 FD 8611 ...

Страница 2: ...ansport E 4 5 Set UP E 5 5 1 General Information E 5 5 2 Condensed Water Pipe E 5 5 3 Sound E 5 6 Installation E 5 6 1 General Information E 5 6 2 Air Connection E 5 6 3 Heating System Connection E 6 6 4 Electrical Connection E 6 7 Start UP E 7 7 1 General Information E 7 7 2 Preparation E 7 7 3 Start Up Procedure E 7 8 Maintenance Cleaning E 8 8 1 Maintenance E 8 8 2 Cleaning the Heating System E...

Страница 3: ...apable of operating the device safely due to their physical sensory or mental abilities or their inexperience or lack of knowledge must not operate this device without supervision or instruction by the person in charge Children must be supervised to ensure that they do not play with the device 1 3 Energy Efficient Use of the Heat Pump With the purchase of this heat pump you are helping to protect ...

Страница 4: ...transferred to the heating water using the liquifier heat ex changer Electrical energy is used to raise the temperature of the heat in the environment to a higher level Because the energy extracted from the air is transferred to the heating water this type of device is called an air to water heat pump The air to water heat pump consists of the main components evaporator ventilator and expansion va...

Страница 5: ...2 Sealing rings for duct connection 3 1 connecting hoses 3 1 double nipples 6 1 flat gaskets 1 1 sealing plug 1 Hose nozzle for filling and drain cock 2 Fixing brackets 2 10 mm dowels 2 8 x 80 screws 4 M4 x 8 screws 1 External sensor 1 6 mm dowels 1 4 5 x 50 screws 4 Transport ATTENTION When transporting the heat pump ensure that it is not tilted more than 45 in any direction Use a wooden pallet f...

Страница 6: ...o prevent solid borne sound from being transmitted to the heat ing system a vibration damped connection should be used for connecting the heat pump with the heating system install the supplied hose connections free of strain Installed air ducts should be sound isolated from the heat pump to prevent the transmission of solid borne sound to the ducts If both air openings are connected directly to a ...

Страница 7: ...be filled de aerated and pressure tested The integrated expansion vessel has a volume of 24 litres This volume is suitable for buildings with a living space area to be heated of maximum 200 m The volume should be checked by the heating system engineer If necessary an additional expansion vessel must be installed according to DIN 4751 Part 1 The tables listed in the manufac turers catalogues simpli...

Страница 8: ... and west sides of the building At least one heating circuit must remain open e g bathroom The overflow valve should be opened far enough to produce the maximum temperature spread between the heating flow and re turn flow listed in the following table for the current heat source temperature The temperature spread should be measured as close as possible to the heat pump The heating element of mono ...

Страница 9: ...from entering the heating sys tem circuit we recommend connecting the flushing device di rectly to the flow and return flow of the liquifier of the heat pump It is important that the system be thoroughly flushed using appro priate neutralising agents to prevent any damage from being caused by cleaning agent residue remaining in the system Acids must be used with great care and all relevant regulat...

Страница 10: ...eating water flow with an internal pressure differential of 2 m h Pa 2 The heat circulating pump is integrated 0 8 2700 1 6 11900 3 9 Free pressure heating circulating pump heating max stage Pa 45000 27000 3 10 Cooling water flow with an internal pressure differential of m h Pa 0 8 2700 1 2 6500 3 11 Free pressure circulating pump cooling max stage Pa 45000 37000 3 12 Air flow rate with an externa...

Страница 11: ...roller Commande régulateur standard A VI 3 2 Steuerung Kühlregler Control of the cooling controller Commande régulateur standard A VII 3 3 Last Load Charge A VIII 3 4 Anschlussplan Standardregler Terminal diagram for the standard controller Schéma électrique du régulateur standard A IX 3 5 Anschlussplan Kühlregler Terminal diagram for the cooling controller Schéma électrique du régulateur refroidi...

Страница 12: ...DJH LQWpULHXU H WpULHXU 5HIOX FRPPXQ QWUpH GDQV OD 3 LOHWDJHV LQW H W 5RELQHW GH UHPSOLVVDJH HW GH YLGDJH pSDUW HDX FKDXGH 6RUWLH GH OD 3 LOHWDJH LQW H W DVVHU DQVFKO VVH DWHU FRQQHFWLRQV 5DFFRUGHPHQWV HDX RQGHQVDWDEODXI VFKODXFK RQGHQVDWH RXWIORZ KRVH 7X DX HDX GH FRQGHQVDWLRQ XIWULFKWXQJ LUHFWLRQ RI DLU IORZ 6HQV G pFRXOHPHQW DLU HGLHQVHLWH 2SHUDWLQJ VLGH Wp GH FRPPDQGH QQHQJHZLQGH 0 LQWHUQDO WK...

Страница 13: ...Q DFFHVVRU RQGXLW G DpUDWLRQ GLVSRQLEOH HQ DFFHVVRLUH 8PODXIHQGH EVFKUlJXQJ EDXVHLWV XU EGLFKWXQJ GHU 6WR NDQWH XQG 9HUEHVVHUXQJ GHU XIWI KUXQJ RQWLQXRXV FKDPIHU WR EH SURYLGHG E WKH FXVWRPHU WR VHDO WKH ERUGHU DQG WR IDFLOLWDWH DLU FLUFXODWLRQ KDQIUHLQ SpULSKpULTXH j IRXUQLU SDU OH FOLHQW DVVXUDQW O pWDQFKpLWp GX ERUG HW DPpOLRUDQW OD FRQGXLWH GH O DLU HL LQVDW HLQHV lPPVWUHLIHQV XQWHU GHU lUPHSX...

Страница 14: ...Q 3D 3HUWH GH SUHVVLRQ HQ 3D HLVWXQJV DKO LQFO 3XPSHQOHLVWXQJVDQWHLO RHIILFLHQW RI SHUIRUPDQFH LQFO SRZHU LQSXW WR SXPS RHIILFLHQW GH SHUIRUPDQFH FRPSULV SDUW GH FRQVRPPDWLRQ GH OD SRPSH HL ZDVVHUGXUFKIOXVV LQ P K HDWLQJ ZDWHU IORZ UDWH LQ P K pELW G HDX GH FKDXIIDJH HQ P K HGLQJXQJHQ Â RQGLWLRQV Â RQGLWLRQV HL ZDVVHUGXUFKVDW HDWLQJ ZDWHU IORZ UDWH pELW G HDX GH FKDXIIDJH P K 9HUIO VVLJHU RQGHQVHU...

Страница 15: ...PDWLRQ GH SXLVVDQFH FRPSULV SDUW GH FRQVRPPDWLRQ GH OD SRPSH UXFNYHUOXVW LQ 3D 3UHVVXUH ORVV LQ 3D 3HUWH GH SUHVVLRQ HQ 3D XIWHLQWULWWVWHPSHUDWXU LQ LU LQOHW WHPSHUDWXUH LQ 7HPSpUDWXUH G HQWUpH G DLU HQ XIWHLQWULWWVWHPSHUDWXU LQ LU LQOHW WHPSHUDWXUH LQ 7HPSpUDWXUH G HQWUpH G DLU HQ HLVWXQJV DKO LQFO 3XPSHQOHLVWXQJVDQWHLO RHIILFLHQW RI SHUIRUPDQFH LQFO SRZHU LQSXW WR SXPS RHIILFLHQW GH SHUIRUPDQFH ...

Страница 16: ...A VI Anhang Appendix Annexes 3 3 Stromlaufpläne Circuit Diagrams Schémas électriques 3 1 Steuerung Standardregler Control of the standard controller Commande régulateur standard ...

Страница 17: ... dimplex de A VII Anhang Appendix Annexes 3 2 3 2 Steuerung Kühlregler Control of the cooling controller Commande régulateur standard HJH 8PVFKDOWYHQWLO RXU ZD UHYHUVLQJ YDOYH 6RXSDSH GH FRPPXWDWLRQ YRLHV ...

Страница 18: ...A VIII Anhang Appendix Annexes 3 3 3 3 Last Load Charge ...

Страница 19: ...www dimplex de A IX Anhang Appendix Annexes 3 4 3 4 Anschlussplan Standardregler Terminal diagram for the standard controller Schéma électrique du régulateur standard ...

Страница 20: ...endix Annexes 3 5 3 5 Anschlussplan Kühlregler Terminal diagram for the cooling controller Schéma électrique du régulateur refroidissement 7HPSHU 7HPS 7HPS HXFKWH XPLGLW XPLGLWp 7HPSHU 7HPS 7HPS HXFKWH XPLGLW XPLGLWp ...

Страница 21: ...ilateur J13 J18 Relaisausgänge zur Ansteuerung der Systemkom ponenten 230 VAC Relay outputs for controlling system components 230 V AC Sorties de relais pour la commande des compo sants du système 230 V AC N2 J1 Stromversorgung N2 24VAC Power supply N2 24 V AC Alimentation en courant N2 24 V AC J2 J3 Sensoreingänge Sensor inputs Entrées de capteurs J4 Analogausgänge werden nicht genutzt Analogue o...

Страница 22: ... terminal block Bornier distributeur charge réseau L N PE 230 V AC 50 Hz commande L N PE 230 V AC 50 Hz distributeur N et PE X2 1 Klemmenleiste Verteiler für 24VAC Terminal strip terminal block for 24 V AC Bornier distributeur distributeur pour 24 V AC X2 2 Klemmenleiste Verteiler für 0VAC Terminal strip terminal block for 0 V AC Bornier distributeur distributeur pour 0 V AC X2 3 Klemmenleiste Ver...

Страница 23: ...www dimplex de A XIII Anhang Appendix Annexes 4 1 4 Hydraulisches Prinzipschema Hydraulic Plumbing Diagram Schéma hydraulique 4 1 Darstellung Schematic view Représentation ...

Страница 24: ...cher Buffer tank Réservoir tampon Wärmepumpenregler Heat pump controller Régulateur de pompe à chaleur Elektroverteilung Electrical distribution system Distributeur courant électrique Warmwasserspeicher Hot water cylinder Ballon d eau chaude Kondensatablauf Condensate outflow Ecoulement des condensats Überdruck Heizwasser Overpressure of the heating water Surpression eau de chauffage E8 Zusatzheiz...

Страница 25: ...www dimplex de A XV Anhang Appendix Annexes 5 5 Konformitätserklärung Declaration of Conformity Déclaration de conformité ...

Страница 26: ...tschland GmbH Geschäftsbereich Dimplex Am Goldenen Feld 18 D 95326 Kulmbach Irrtümer und Änderungen vorbehalten Subject to alterations and errors Sous réserve d erreurs et modifications 49 0 9221 709 565 www dimplex de ...

Отзывы: