Shaft Packing Replacement
Removal of the valve from the line for shaft packing replacement is not required as long as the shaft is
accessible.
1.
Relieve the pressure in the pipeline and close the valve.
2.
If needed, remove Counterweight Lever Arm Fabrication (B54), spring Lever Arm Fabrication
(B33 or B85) or Cushion Lever (B88). Then, remove the Gland Nuts (A26) and Gland (A25)
from Shaft (A13).
3.
Remove Long Flat Key (B78) from extended shaft.
4.
Remove the V-Type Packing Sets (A23) with a flexible packing hook or similar tool. Clean the
packing area, being careful not to damage it.
5.
Obtain the proper size packing from the parts list. Cut the packing rings to fit around the shaft.
Install one ring at a time. Make sure it is clean and has not picked up any dirt in handling before
installing it. Lubricate I.D. of each packing ring. Each ring should be firmly seated with a tamping
tool. Do not depend on the packing gland entirely to seat the set of rings properly. This practice
will jam the last rings installed but leave the first ones loose in the box.
6.
See “Shaft Packing Adjustment” section to adjust packing after replacing.
Disc Seat Replacement
Servicing the valve while the pipeline is under pressure can cause personal injury or
equipment damage. Relieve pipeline pressure before servicing the valve.
1.
Relieve the pressure in the pipeline and close the valve.
2.
Remove Seat Retaining Ring (A16) from Disc (A10).
3.
Remove old Disc Seat (A15) and replace with new Disc Seat.
4.
Re-install Seat Retaining Ring (A16).