Monitor Calibration Unit
Operation Instructions

Description

The Desco 

98220

 Monitor Calibration Unit is designed to 

simplify the process of calibrating Workstation Continuous 

Monitors.  The unit allows the user to quickly and easily 

verify whether a tester is operating within specifications.  The 

Monitor Calibration Unit is a passive device and requires no 

power source.
“A Compliance Verification Plan shall be established 

to ensure the Organization’s fulfillment of the technical 

requirements of the ESD Control Program Plan (ANSI/

ESD S20.20-2007 section 7.3).  The product qualification 

for the Continuous Monitors per ANSI/ESD S20.20-2007 

Table 3 is “User defined” test method and required limits, 

and compliance verification is per ESD TR53 with the 

required limit being “Manufacturer defined.”  Per ESD TR53 

Compiance Verification “Compliance verification of the 

constant monitor device should follow the manufacturer’s 

instructions.”

Packaging

1  Monitor Calibration Unit

1  Alligator Clip

1  Stacking Snap Banana Jack Adapter

1  Banana Jack to Wire Adapter

1  Certificate of Calibration

Calibration Test Procedures

The Monitor Calibration Unit was specifically designed for 

use in calibration of Desco brand equipment.  The following 

step by step procedures will cover calibration for specific test 

units.  The procedures will not cover adjustment of the test 

equipment.  For detailed information regarding adjustment of 

specific Desco brand testers contact our Customer Service 

Department at 909-627-8178.

  TECHNICAL BULLETIN TB-2082 

Calibrating the Full Time Continuous Monitor

The Full Time Continuous Monitor is available as following 

item number:

Figure 1. Desco 

98220

 Monitor Calibration Unit

Rev. December 2009

Item

Voltage

19225

120 VAC

TESTING THE OPERATOR CIRCUIT
Step 1:

  Connect the Calibration Unit’s banana plug wire 

labeled “GROUND” to a known ground.  Do not plug the 

ground lead from the Calibration Unit to the monitor’s 

common point ground banana jack.  There is a 47 kilohm 

resistance to ground.

Step 2:

  Insert the Calibration Unit’s banana plug labeled 

“OPERATOR” into the jack labeled “OPERATOR” on the Full 

Time Continuous Monitor (see Figure 2).  Power the monitor.

Figure 2. Connecting the OPERATOR test lead from 
the Monitor Calibration Unit to the Full Time Continuous 
Monitor

Step 3:

 Start the Calibration Unit’s selector knob at the full 

counter-clockwise position.  When testing the OPERATOR 

circuit, test only the first four limits on the Calibration Unit.  

Rotate the selector knob to the “LOW FAIL” position; the 

red “OPERATOR GROUND” LED on the monitor should 

illuminate and alarm.

Test Equipment Depot - 800.517.8431 - 99 Washington Street Melrose, MA 02176 - TestEquipmentDepot.com 

Содержание TB-2082

Страница 1: ...brand equipment The following step by step procedures will cover calibration for specific test units The procedures will not cover adjustment of the test equipment For detailed information regarding adjustment of specific Desco brand testers contact our Customer Service Department at 909 627 8178 TECHNICAL BULLETIN TB 2082 Calibrating the Full Time Continuous Monitor The Full Time Continuous Monit...

Страница 2: ...uous Monitor Step 3 Rotate the Calibration Unit s knob switch to the MAT FAIL 10M position The monitor s red MAT GROUND LED should illuminate and the alarm should sound Step 4 Rotate the selector knob counter clockwise to the MAT PASS 10M position The monitor s MAT GROUND green LED should illuminate Item Voltage 19232 120 VAC 19233 220 VAC Note If calibrating discontinued items 19208 or 19209 disc...

Страница 3: ...nana lead Step 5 Repeat this procedure for the remaining satellite remote Calibrating the Jewel Workstation Continuous Mini Monitor The Jewel Workstation Continuous Mini Monitor is available as following item numbers Figure 5 Connecting the MAT test lead from the Monitor Calibration Unit to the satellite remote Step 3 Rotate the Calibration Unit s knob switch to the MAT FAIL 10M position The monit...

Страница 4: ...tion The monitor s red WORKSURFACE GROUND LED should illuminate and the alarm should sound Step 4 Rotate the selector knob counter clockwise to the MAT PASS 500M position The monitor s WORKSURFACE GROUND green LED should illuminate Note During FAIL LOW and FAIL HIGH the monitor will continuously alarm until the banana lead is removed from the satellite remote The alarm will shut off approximately ...

Страница 5: ...us Mini Monitor 19213 19214 19215 19216 19217 Multi Mount Continuous Monitor 19220 19221 19222 19223 98225 98226 98227 98228 Calibration Required Test Equipment RLC Bridge Settings For 50 Hz Frequency 1 000 Hz 20 x 50 20th Harmonic For 60 Hz Frequency 1 020 Hz 17 x 60 17th Harmonic Set function switch to read equivalent parallel circuit Additional Required Test Equipment for 98220 MAT Resistance M...

Страница 6: ...roximately two weeks If your unit is out of warranty call our Customer Service Department at 909 627 8178 Chino CA or 781 821 8370 Canton MA for a Return Material Authorization RMA and proper shipping instructions and address Desco will quote repair charges necessary to bring your unit up to factory standards Warranty Exclusions THE FOREGOING EXPRESS WARRANTY IS MADE IN LIEU OF ALL OTHER PRODUCT W...

Отзывы: