background image

Mounting instructions 

To  ensure  correct  mounting,  and  to  obtain  the  intended  functionality  of  your  product,  DEIF  A/S 
recommends that you read these guidelines carefully before you mount the product. 
Use the correct tools for mounting, and do not exceed the recommended tightening torques. 
 

DEIF A/S warranty will be lost for products that are damaged because of incorrect tools used 
for mounting, or because of excessive tightening of the terminals and screws. 

 

Tools

 

 

Do not use electric screwdrivers 

 

Only use two fingers on the screwdriver 

 
 

Tightening torques 

For terminals: Max. 0.5 Nm 

 

For mounting screws: Max. 0.5 Nm 

 

 

Installation

 

Verification: 

Verify that the instrument configuration is according to application.

 

 
Aux. supply:

 Connect terminals to correct voltage. 

 

Measuring  circuit:

  Connect  PE  to  ground  and  L-  to  the  positive  or  negative  terminal  of  the 

monitored network. 
 

Warning: 

If a high-voltage “MEGGER” is used, the ADL must be disconnected before testing is 
carried out. Omitting this may result in damage to the ADL. 

 

Test

  

An instrument self-test can be carried out according to IEC 61557-8 as shown in 

Fig. 1

 below. Test 

resistor = 1 kΩ/0.25 W (recommended value). 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
 
Fig. 1 

 

Adjustment of the set point 

A new feature in variants 04, 05 and 06 makes accurate setting of set point much easier. When the 
set point potentiometer at the rear of the instrument is turned, the insulation monitor automatically 
goes to meter indication of set point during setting and power-up. 
As soon as the set point potentiometer is turned, the insulation monitor enters setting mode. This is 
indicated by the fast flashing of the SUPERVISION LED, and by the meter pointer showing the set 
point setting instead of actual measurement. 
When the desired set point level is reached, the product automatically returns to normal measuring 
mode after a few seconds, by which the SUPERVISION LED stops flashing fast, and the meter 
pointer returns to normal reading. 
 

Set point test/control: 

During power-up, for a few seconds, the meter pointer shows the actual set 

point setting while the SUPERVISION LED is flashing fast. This function enables a test function for 
fast control of settings from the front of the switchboard.

 

 