Safety Note

To avoid injury and damage to persons 

and devices, it is absolutely necessary 

these instructions are carefully read and 

observed prior to assembly and commissioning. 
Necessary assembly, start-up, and maintenance 

work must be performed only by qualified, 

trained and authorised personnel. 
Prior to assembly and maintenance work on the 

controller, the system must be:

- depressurized 

-  cooled down

- emptied 

- cleaned

Please comply with the instructions of the 

system manufacturer or system operator.

Disposal instruction

This product should be 

dismantled and its 

components sorted, if 

possible, in various groups 

before recycling or disposal. 

Always follow the local disposal regulations.

Definition of Application

The controller is used for differential 

pressure control of water and water glycol 

mixtures for heating, district heating and 

cooling systems. 

The technical data on the rating plates 

determine the use.

Scope of Delivery

Assembly kit PCV-VFGS 2:  

•  main valve assembled with valve body 

extension and seal pots, 

•  throttling element, 

•  impulse tube (throttle to seal pot of main 

actuator) 

To order additionally: 

•  pilot valve, 

•  pilot valve actuator, 

•  seal pot for pilot valve for T<150 °C

•  impulse tubes for a pilot valve, 

•  flange tailpieces. 

Not included: 

•  bypass pipes, 

•  flat gaskets, 
•  screws/nuts. 

Bypass pre-assembly 

1.  Connect a throttling element to the pilot 

valve flange to flange. 

2.  Align flow direction – throttle in front of the 

pilot valve.  

3.  Align valve actuator and throttle impulse 

connection as shown on a drawing.

Bypass assembly  

1.  Prepare flange tailpieces and pipes for 

welding 

.  

2.  Join bypass pipes to weld tailpieces 

, do 

the welding 

.  

3.  Use flat gaskets and screws/nuts to assemble 

bypass pipeline. Align pipes and valve as 
shown on a drawing 

.  

Holes for bypass  

Mark connection points on a main pipe 

and drill holes for bypass flow.

Connect bypass  

1.  Make a join 

2.  Align main and bypass media flow direction.

3.   Remove main valve and weld bypass pipe to 

main pipe 

.

4.  Return main valve 

, check flow orientation.

Main impulse tube mounting 

Connect impulse tube from throttling element 

to seal pot of a main valve pressure actuator.

Lean impulse tubes into holes on throttle 

element and seal pot. Cut one or both 

 

to align 

 and debur cut edge. Then cut 

one or both to align for a joining piece and 

debur cut edge 

. Add the joining piece 

and tighten all four nuts 

.

Pilot impulse tube mounting  

1.  Put the steel ring into copper impulse tube 

, press it completely in. 

2.  Immerse the end into connection screw 

 

and tighten with a key 

Note:

At max teperatures ≥ 150 °C use a seal pot and connect it 
to main flow with stainless steal impulse tube. 

Connect pilot valve impulse tubes 

for controllers 

ENGLISH

Installation Guide 

Assembly kit PCV-VFGS 2 DN 150-250

Produced by Danfoss A/S  © 10/2013

VI.JA.N1.02