6 - CLEANING
6.0 General information

The firebox and the flues must be periodically cleaned from the combustion solid residues

(ashes).

Keeping the flues free from ashes ensure the draught efficacy and then the best efficiency of 

the
heat .

6.1 Operation mode and periodicity

Firebox: The check and the cleaning of the amount of combustion residues in the
firebox [3] must be carried out every day by opening the door [6]. The
combustion residues in the low part [4] must be cleaned by opening the door
[5].
Tube nest: The check and the cleaning of the amount of combustion residues in the tube
nest [8] must be carried out about every 4-5 days, by opening the door[7] and
using the proper brush supplied with the machine.
Fume pipe fittings: The check and the cleaning of the amount of combustion residues in the
fume pipe fitting [16] must be carried out every 15 days by means of the ash removal little
door [15]. Check and clean the flue periodically.

6.2 Cleaning of the fuel hopper

The fuel hopper is equipped of a hinged lid. The cleaning of the fuel hopper [16] must be
carried out only after stopping the machine, removing the hopper from the flange that 

connect it
to the screw.

BEFORE OPENING THE MACHINE MAKE SURE THE FUEL CONTAINED IN THE
FIREBOX IS COMPLETELY EXTINGUISHED

7 - MAINTENANCE
7.0 General information

The heat generator must be subjected to regular maintenance. The maintenance must be carried
out by specialised staff.

7.1 Periodical maintenance

At the beginning of every season clean the fan blades (The accumulation of dust and other material
on the fan blades decreases the efficiency and compromises the balancing, causing vibrations and

noises)

Содержание CSL25

Страница 1: ...TERMOMECCANICA C da Cerreto 25 B MIGLIANICO CH Phone 39 0871 950329 Fax 39 0871 950687 SOLID FUEL HEAT GENERATOR SERIE CSL Models from 25 to 100 USE AND MAINTENANCE MANUAL www recal cl bio recal cl 5...

Страница 2: ...2 DESCRIPTION of the MACHINE PAGE 6 3 MACHINE GENERAL DATA PAGE 7 4 TRANSPORT HANDLING INSTALLATION PAGE 8 5 STARTING PAGE 9 6 CLEANING PAGE 10 7 MANTEINANCE PAGE 10 8 NOICE PAGE 11 9 PUTTING OUT OF S...

Страница 3: ...4 Technical Normative A N C C collection R 1978 D M 01 012 1975 0 4 Identification of the manufacturer The identification of the company D Alessandro Termomeccanica as Manufacturer is indicated accor...

Страница 4: ...Lack of maintenance as prescribed into this manual Failures and or breaks not due to the malfunction of the machine itself Reasons not due to the manufacturer The warranty is valid only to the origin...

Страница 5: ...chine has been conceived planned and built according to all the Safety Standards Although any possible reason of risk has been considered it is possible that besides the risks deriving from improper u...

Страница 6: ...t can be reached by means of an insulated door 6 the tube nest 8 that can be reached too for the cleaning operations trough the door 7 and the fume pipe fittings 16 The warm water delivery 9 and backf...

Страница 7: ...L100 115 100 Water Connections Model A mm B mm C mm D mm Flue mm Water Content l Gas DN CSL25 700 820 1400 1350 200 75 1 1 2 40 CSL40 700 920 1400 1350 200 100 1 1 2 40 CSL60 700 1170 1400 1350 200 14...

Страница 8: ...for the coupler with slings pict 2 4 3 Installation and testing Only when the machine is completely installed that is only when it is positioned and levelled connected to the hydraulic circuit connect...

Страница 9: ...l and the cock be provide with anti calcareous device The circulation pump work regularly ensuring the reduction of the water temperature in the boiler in case of overheating 5 2 Starting After perfor...

Страница 10: ...machine Fume pipe fittings The check and the cleaning of the amount of combustion residues in the fume pipe fitting 16 must be carried out every 15 days by means of the ash removal little door 15 Chec...

Страница 11: ...inlet Tube nest door 1 www recal cl bio recal cl 562 2430 7700 8 NOISE 8 0 General information The machine acoustic radiation pressure are not significant 8 1 Sound emission values Measurements carri...

Страница 12: ...11 2 PEFORMANCE OF THE INSTALLER 11 2 1 I S P E S L NOTIFICATION The thermal system for boilers with nominal output more than 34 8 KW 30 000 Kcal h must be done according a project decided by qualifie...

Страница 13: ...s The definition of the machine contained into the Directive 98 37 EEC can be applied to the heat generator for solid fuel The Declaration of conformity and the EC mark certify the machine complying w...

Страница 14: ...dictation however applicable it is of the Machine Directive 89 392 EEC 98 37 EEC Machines Safety 89 336 EEC 92 31 EEC 93 97 EEC Electromagnetic Compatibility CEI EN 60204 1 44 5 boards and devices on...

Отзывы: