DAIREN SQW 12-4ND Скачать руководство пользователя страница 10

Operation Manual of 12V UPS

 

 

 

 

 

Revision: 01

 

Date: Dec.5. 2021

 

Page 

10 

of 

10

 

9) 

Battery Installation and Wiring 

9.1    Ensure the 

INPUT MCB

 and 

OUTPUT MCB

 on the UPS door panel   

and  the 

MAINTENANCE  SWITCH

  on  the  PCB  card  must  be  at  off 

position . 

9.2   

The positive and negative wires of the battery are installed on the 

BATT+ and BATT- of the PCB card respectively.

 

9.3    Connect the battery cables one by one and confirm the positive and 

negative polarity of the battery.

 (

Figure 1) 

9.4    Arrange  the  battery  cable  and  push  the  battery  into  the  cabinet 

battery compartment.(Figure 2) 

9.5    Battery installation and wiring completed. 

Note: Before turn on OUTPUT MCB , must ensure the AC load is not short 
circuited or overloaded (more than 80W) 

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Figure 1 

Figure 2 

Содержание SQW 12-4ND

Страница 1: ...Operation Manual of 12V UPS Revision 01 Date Dec 5 2021 Page 1 of 10 Uninterruptible Power Supply UPS EBOPS Vision Model SQW 12 4ND...

Страница 2: ...at the same time provides supply to the load during normal conditions Figure 1 Emergency Mode The battery will restore its energy in the form of DC currents to the inverter and the inverter will supp...

Страница 3: ...line wire 1 5 220V_N Mains neutral wire 1 5 E Earth wire 2 5 LS LT Loads line wire 1 5 NS NT Loads neutral wire 1 5 BAT Battery positive 4 0 BAT Battery negative 4 0 P1 P2 DC loads positive 1 5 N1 N2...

Страница 4: ...Operation Manual of 12V UPS Revision 01 Date Dec 5 2021 Page 4 of 10 12VDC Output Max output current 1 5A 24VDC Battery 12VDC Output 12VDC Output...

Страница 5: ...reshold during the float charging the UPS charging voltage will be reduced to compensate for the temperature increase 3 2 Installation It is necessary to tape the metal probe of the battery temperatur...

Страница 6: ...he button Timer Switch the LED panel will display the voltage and current for 4 hours 5 Definitions of MCB The Input MCB is installed on the left side of the door panel and will input 230VAC to the UP...

Страница 7: ...ctifier and also to cut off the DC supply to the inverter during maintenance This battery switch must be turned off when the battery is replacing Likewise It is also recommended to turn off all UPS ci...

Страница 8: ...ttery Switch and the following can be observed a The DC Voltmeter will indicate the battery terminal voltage b The MAINS ON LED indicator on the panel lights up c The DC Ammeter will reflect to the ba...

Страница 9: ...time the mains Green LED indicator goes off 2 The DC Ammeter will reflect the battery output discharge current 3 If required to test the UPS for longer duration the AC supply to the UPS is advisable...

Страница 10: ...ires of the battery are installed on the BATT and BATT of the PCB card respectively 9 3 Connect the battery cables one by one and confirm the positive and negative polarity of the battery Figure 1 9 4...

Отзывы: