Components
Service manual
214
REYQ8~20+REMQ5U7Y1B
VRV IV+ Heat Recovery
ESIE18-15B – 2020.05
3.2 Branch selector box PCB
3.2.1 Checking procedures
INFORMATION
It is recommended to perform the checks in the listed order.
To perform a power check of the branch selector box PCB
Prerequisite:
Stop the unit operation via the central controller.
Prerequisite:
Turn OFF the respective circuit breaker.
Prerequisite:
Remove the required plate work, see
315].
1
Turn ON the power of the unit.
2
Measure the voltage on connector X1A of the branch selector box PCB. The
voltage MUST be 230 V AC±10%.
BS1Q-A
a
a
Connector X1A
BS4~16Q-A
a
a
Connector X1A
Does the Branch selector box PCB
receive power?
Action
Yes
selector box PCB and continue with the
next procedure.
No
Continue with the next step.