Preparation
Installer reference guide
12
RZAG71~Y1
Sky Air Alpha-series
4P573381-1 – 2019.04
Requirement
Limit
71
100
125+140
5 Maximum difference between branch
lengths
Pair: N/A
—
Twin: L2–L3≤Limit
10 m
Triple: L2–L4≤Limit
—
10 m
Double twin:
▪ L2–L3≤Limit
▪ L4–L5≤Limit
▪ L6–L7≤Limit
▪ (L2+L4)–(L3+L7)≤Limit
—
10 m
6 Maximum height between indoor and
outdoor
Pair, twin, triple and double twin: H1≤Limit
30 m
7 Maximum height between indoors
Pair: N/A
Twin, triple and double twin: H2≤Limit
0.5 m
(a)
Parenthesised figure represents the equivalent length.
Example
If the system layout is as follows…
Then the requirements are…
▪ RZAG125
▪ Triple:
L2
L3
L4
H1
H2
L1
▪ Ø standard
1
3 m≤L1+L4
2
L1+L2≤85 m (100 m)
3
L1+L2+L3+L4≤85 m
4
L2≤20 m
5
L2–L4≤10 m
6
H1≤30 m
7
H2≤0.5 m
5.3.2
Refrigerant piping insulation
▪ Use polyethylene foam as insulation material:
▪ with a heat transfer rate between 0.041 and 0.052 W/mK (0.035
and 0.045 kcal/mh°C)
▪ with a heat resistance of at least 120°C
▪ Insulation thickness
Ambient
temperature
Humidity
Minimum thickness
≤30°C
75% to 80% RH
15 mm
>30°C
≥80% RH
20 mm
5.4
Preparing electrical wiring
5.4.1
About preparing electrical wiring
INFORMATION
Also read the precautions and requirements in the
"General safety precautions" chapter.
INFORMATION
Also read
"6.7.5 Specifications of standard wiring
WARNING
▪ If the power supply has a missing or wrong N-phase,
equipment might break down.
▪ Establish proper earthing. Do NOT earth the unit to a
utility pipe, surge absorber, or telephone earth.
Incomplete earthing may cause electrical shock.
▪ Install the required fuses or circuit breakers.
▪ Secure the electrical wiring with cable ties so that the
cables do NOT come in contact with sharp edges or
piping, particularly on the high-pressure side.
▪ Do NOT use taped wires, stranded conductor wires,
extension cords, or connections from a star system.
They can cause overheating, electrical shock or fire.
▪ Do NOT install a phase advancing capacitor, because
this unit is equipped with an inverter. A phase
advancing capacitor will reduce performance and may
cause accidents.
WARNING
▪ All wiring MUST be performed by an authorised
electrician and MUST comply with the applicable
legislation.
▪ Make electrical connections to the fixed wiring.
▪ All components procured on-site and all electrical
construction MUST comply with the applicable
legislation.
WARNING
ALWAYS use multicore cable for power supply cables.