6 Installation

Installer reference guide

11

35R5V1B RXM20~35R5V1B
R32 Split Series
4P519439-8H – 2020.07

5.3

Preparing refrigerant piping

5.3.1

Refrigerant piping requirements

INFORMATION

Also  read  the  precautions  and  requirements  in  the
"General safety precautions" chapter.

Piping material:

 Phosphoric acid deoxidised seamless copper.

Piping diameter:

Liquid piping

Ø6.4 mm (1/4")

Gas piping

Ø9.5 mm (3/8")

Piping temper grade and thickness:

Outer diameter

(Ø)

Temper grade

Thickness (t)

(a)

6.4 mm (1/4")

Annealed (O)

≥0.8 mm

t

Ø

9.5 mm (3/8")

Annealed (O)

(a)

Depending on the applicable legislation and the maximum
working pressure of the unit (see "PS High" on the unit name
plate), larger piping thickness might be required.

5.3.2

Refrigerant piping insulation

▪ Use polyethylene foam as insulation material:

▪ with a heat transfer rate between 0.041 and 0.052 W/mK (0.035

and 0.045 kcal/mh°C)

▪ with a heat resistance of at least 120°C

▪ Insulation thickness

Pipe outer diameter

p

)

Insulation inner

diameter (Ø

i

)

Insulation thickness

(t)

6.4 mm (1/4")

8~10 mm

≥10 mm

9.5 mm (3/8")

12~15 mm

Ø

i

Ø

i

t

Ø

p

Ø

p

If  the  temperature  is  higher  than  30°C  and  the  humidity  is  higher
than RH 80%, the thickness of the insulation materials should be at
least  20  mm  to  prevent  condensation  on  the  surface  of  the
insulation.

5.4

Preparing electrical wiring

5.4.1

About preparing electrical wiring

INFORMATION

Also  read  the  precautions  and  requirements  in  the
"General safety precautions" chapter.

INFORMATION

Also  read 

"6.7.4  Specifications  of  standard  wiring

components" 

[

4

 19].

WARNING

▪ If  the  power  supply  has  a  missing  or  wrong  N-phase,

equipment might break down.

▪ Establish  proper  earthing.  Do  NOT  earth  the  unit  to  a

utility  pipe,  surge  absorber,  or  telephone  earth.
Incomplete earthing may cause electrical shock.

▪ Install the required fuses or circuit breakers.

▪ Secure  the  electrical  wiring  with  cable  ties  so  that  the

cables  do  NOT  come  in  contact  with  sharp  edges  or
piping, particularly on the high-pressure side.

▪ Do  NOT  use  taped  wires,  stranded  conductor  wires,

extension  cords,  or  connections  from  a  star  system.
They can cause overheating, electrical shock or fire.

▪ Do  NOT  install  a  phase  advancing  capacitor,  because

this  unit  is  equipped  with  an  inverter.  A  phase
advancing  capacitor  will  reduce  performance  and  may
cause accidents.

WARNING

▪ All  wiring  MUST  be  performed  by  an  authorised

electrician  and  MUST  comply  with  the  applicable
legislation.

▪ Make electrical connections to the fixed wiring.

▪ All  components  procured  on-site  and  all  electrical

construction  MUST  comply  with  the  applicable
legislation.

WARNING

ALWAYS use multicore cable for power supply cables.

6

Installation

6.1

Overview: Installation

This  chapter  describes  what  you  have  to  do  and  know  on-site  to
install the system.

Typical workflow

Installation typically consists of the following stages:

1

Opening the unit

2

Mounting the outdoor unit

3

Connecting the refrigerant piping

4

Checking the refrigerant piping

5

Charging refrigerant

6

Connecting the electrical wiring

7

Finishing the outdoor unit installation

6.2

Opening the units

6.2.1

About opening the units

At certain times, you have to open the unit. 

Example:

▪ When connecting the refrigerant piping

▪ When connecting the electrical wiring

▪ When maintaining or servicing the unit

DANGER: RISK OF ELECTROCUTION

Do NOT leave the unit unattended when the service cover
is removed.

Содержание RXM20R5V1B

Страница 1: ...Installer reference guide R32 Split Series English Installer reference guide R32 Split Series RXM20R5V1B RXM25R5V1B RXM35R5V1B ARXM25R5V1B ARXM35R5V1B...

Страница 2: ...15 6 5 3 To check for leaks 16 6 5 4 To perform vacuum drying 16 6 6 Charging refrigerant 16 6 6 1 About charging refrigerant 16 6 6 2 About the refrigerant 17 6 6 3 Precautions when charging refriger...

Страница 3: ...er operation It could be too hot or too cold Give it time to return to normal temperature If you must touch it wear protective gloves Do NOT touch any accidental leaking refrigerant WARNING Improper i...

Страница 4: ...ed in the duct work air inlet AND outlet are connected directly to the same room by ducting Do NOT use spaces such as a false ceiling as a duct for the air inlet or outlet NOTICE Precautions shall be...

Страница 5: ...7 8 38 5 4 2 150 7 8 518 4 4 12 3 7 956 40 1 4 4 165 7 956 539 m kg Amin m2 4 6 20 0 4 8 21 8 5 0 23 6 1 842 5 2 25 6 1 843 4 45 5 4 27 6 2 0 4 83 5 6 29 7 2 2 5 31 5 8 31 8 2 4 5 79 6 0 34 0 2 6 6 39...

Страница 6: ...form may prevent normal operation CAUTION When the refrigerant charging procedure is done or when pausing close the valve of the refrigerant tank immediately If the valve is NOT closed immediately rem...

Страница 7: ...lers Documentation set This document is part of a documentation set The complete set consists of General safety precautions Safety instructions that you MUST read before installing Format Paper in the...

Страница 8: ...he accessories at the bottom of the package 1 1 1 1 1 1 b e c d a f a General safety precautions b Outdoor unit installation manual c Fluorinated greenhouse gases label d Multilingual fluorinated gree...

Страница 9: ...NING Do NOT place objects below the indoor and or outdoor unit that may get wet Otherwise condensation on the main unit or refrigerant pipes air filter dirt or drain blockage may cause dripping and ob...

Страница 10: ...winds Example Behind the building b c a If the outdoor unit is exposed to direct sea winds install a windbreaker Height of windbreaker 1 5 height of outdoor unit Mind the service space requirements wh...

Страница 11: ...e equipment might break down Establish proper earthing Do NOT earth the unit to a utility pipe surge absorber or telephone earth Incomplete earthing may cause electrical shock Install the required fus...

Страница 12: ...se a vibration proof rubber field supply in cases where vibrations may be transmitted to the building Fix the unit securely by means of foundation bolts in accordance with the foundation drawing Prepa...

Страница 13: ...when connecting the refrigerant piping INFORMATION Also read the precautions and requirements in the following chapters General safety precautions Preparation DANGER RISK OF BURNING SCALDING CAUTION...

Страница 14: ...t refrigerant gas leakage Use flare nuts that are included with the unit Using different flare nuts may cause refrigerant gas leakage 1 Cut the pipe end with a pipe cutter 2 Remove burrs with the cut...

Страница 15: ...ervice port 2 Connect the gas refrigerant connection from the indoor unit to the gas stop valve of the outdoor unit NOTICE It is recommended that the refrigerant piping between indoor and outdoor unit...

Страница 16: ...ying again NOTICE Make sure to open the stop valves after installing the refrigerant piping and performing vacuum drying Running the system with the stop valves closed may break the compressor INFORMA...

Страница 17: ...To determine the complete recharge amount INFORMATION If a complete recharge is necessary the total refrigerant charge is the factory refrigerant charge see unit name plate the determined additional a...

Страница 18: ...o NOT branch the power supply for the drain pump etc from the terminal block This could result in electrical shock or fire WARNING Keep the interconnection wiring away from copper pipes without therma...

Страница 19: ...ck or leakage 3 Open the wire clamp 4 Connect the interconnection cable and power supply as follows 50 Hz 220 240 V c d f a b e a Interconnection cable b Power supply cable c Circuit breaker d Earth l...

Страница 20: ...be closed Power up the unit after it is closed The indoor unit is properly mounted The outdoor unit is properly mounted The system is properly earthed and the earth terminals are tightened The power s...

Страница 21: ...t least once a year However applicable legislation might require shorter maintenance intervals NOTICE Applicable legislation on fluorinated greenhouse gases requires that the refrigerant charge of the...

Страница 22: ...e connection of the earth wiring 11 3 5 Symptom Unit does NOT function or burn damage Possible causes Corrective action The wiring was NOT performed in accordance with the specifications Correct the w...

Страница 23: ...orced cooling a c b d d e a Gas stop valve b Closing direction c Hexagonal wrench d Valve cap e Liquid stop valve 12 3 To start and stop forced cooling There are 2 methods to perform forced cooling Me...

Страница 24: ...TCH E H HEATER F U FU FOR CHARACTERISTICS FUSE REFER TO PCB INSIDE YOUR UNIT FG CONNECTOR FRAME GROUND H HARNESS H P LED V L PILOT LAMP LIGHT EMITTING DIODE HAP LIGHT EMITTING DIODE SERVICE MONITOR GR...

Страница 25: ...r application explaining how to install configure and maintain it Operation manual Instruction manual specified for a certain product or application explaining how to operate it Maintenance instructio...

Страница 26: ......

Страница 27: ......

Страница 28: ...ANBUL T RK YE Tel 0216 453 27 00 Faks 0216 671 06 00 a r Merkezi 444 999 0 Web www daikin com tr G lsuyu Mahallesi Fevzi akmak Caddesi Bur ak Sokak No 20 34848 Maltepe 4P519439 8H 2020 07 Copyright 20...

Отзывы: