Start-up
5.2
Checklists for start-up
Checklist before start-up
1.
Is the ROTEX A1 BO correctly set up according to an admissible set up variant and without visible damages?
yes
2.
When using a pressure assembly: Is the installation site additionally secured (leakproof tray, filter cup of metal)?
yes
3.
Combustion air supply secured?
yes
4.
Adequate ventilation and extraction in the heating room with limited room-air independent (separate flue
gas/intake air) or room-air dependent operation?
yes
5.
Does the mains connection conform to the specifications?
yes
6.
Is the mains voltage 230 V, 50 Hz?
yes
7.
Flue gas line connected correctly with a consistent gradient (at least 3°) and no leaks?
yes
8.
Condensate box correctly connected, filled with water and leakproof?
yes
9.
On restoration: Heat distribution network flushed out? Sludge separator fitted in heating return?
yes
10. Is the diaphragm expansion tank mounted according to specifications and of the requisite size?
yes
11. Is the safety valve connected to a safe free drain?
yes
12. Has the quality of the filling water been checked and has any necessary water preparation been carried out?
yes
13. System water pressure within prescribed range?
yes
14. Are boiler and heating system vented?
yes
15. In case of systems with a hot water storage tank:
a) Storage tank filled?
yes
b) Is the 3-way diverter valve correctly mounted on the flow connection and PCB plug inserted?
yes
16. Are all sensors connected and correctly positioned?
yes
17. Mixer group, mixer module and mixer circuit sensor (optional) connected correctly?
yes
18. Room controller (optional) correctly connected to the PCB?
yes
19. Oil connection connected correctly and properly in accordance with regulations and checked for leaks?
yes
20. Oil tank adequately filled and oil valves opened?
yes
The system may only be started up if all questions can be answered with "Yes".
Checklist after start-up
A
Is the heating circulation pump running? Is the heater heating up?
yes
B
Is the oil line vented?
yes
C
Is the oil pressure within the permissible range?
yes
D
Have the burner settings been checked by using a flue gas analyser and readjusted if necessary?
yes
E
Has the resistance of the flue gas pipe been measured and if so, is the measured resistance higher than the re-
quired minimum resistance?
yes
F
In case of systems with a hot water storage tank: Has the 3-way diverter valve connector been plugged on fol-
lowing start-up?
yes
The system may only be handed over to the user/owner if all questions can be answered with "Yes".
Ɣ
Fill out the enclosed installation and instruction form as well as the first pages of the operating manual together with the.