6
|
Unit installation
Installer reference guide
24
FTXP-N
Daikin room air conditioner
4P518023-14L – 2022.06
INFORMATION
The removed pipe port cover can be kept in the mounting plate pocket.
(mm)
d
e
d
a
c
a
c
a
g
h
f2
a
a
i
f1
b
e
a
Recommended mounting plate fixing spots
f1
Measure point for piping hole center " " (to left)
b
Pocket for the pipe port cover
f2
Measure point for piping hole center " " (to right)
c
Tabs for placing a spirit level
g
Gas pipe end
d
Through-the-wall hole Ø80 mm
h
Liquid pipe end
e
Drain hose position
i
Center of the unit
6.3.2 To drill a wall hole
CAUTION
For walls containing a metal frame or a metal board, use a wall embedded pipe and
wall cover in the feed-through hole to prevent possible heat, electrical shock, or fire.
NOTICE
Be sure to seal the gaps around the pipes with sealing material (field supply), in order
to prevent water leakage.
1
Drill a 80 mm large feed-through hole in the wall with a downward slope
towards the outside.
2
Insert a wall embedded pipe into the hole.
3
Insert a wall cover into the wall pipe.
Ø80
a b
c
a
Wall embedded pipe (field supply)
b
Putty (field supply)
c
Wall hole cover (field supply)
4
After completing wiring, refrigerant piping and drain piping, do NOT forget to
seal the gap with putty.