Ducted Air Conditioners

Installation Manual

-6

  Press ON/OFF button within about

  10 seconds. The test operation starts.

  Check operation condition for

  3 minutes.
 

*

 Note) In the case of above men-

              tioned procedures 

7-5 

and

             

 7-6

 in reverse order, test

              operation can start as well.

-7

  Press Airflow Setting button.

-8

  Select airflow direction setting by

  pressing the “     “ button on the setting

 screen. 

  Use the “        “ buttons to change the 

  airflow direction.

-9

  After the operation of airflow direction

  is confirmed, press Menu/Enter button.

  Basic screen returns.

-10

  Press and hold Cancel button for 

 

4 seconds or longer in the Basic 

 screen.

 

Service Settings menu is displayed.

-11

 Select  

Test Operation

  in the Service 

 

Settings menu, and press Menu/Enter

 

button. Basic screen returns and

   normal operation is conducted.
 

*

 Note) Test operation will automatically 

finish in 30 minutes.

-12

  Check the functions according to the

 

operation manual.

-13

 

When the decoration panel is not

 

installed, turn off the power after the

 

test operation finishes.

 

If the interior finish work is not completed

when the test operation is finished, for 

protection of the air conditioner ask the

customer not to operate the air conditioner

until the interior finish work is completed.

If the air conditioner is operated, the inside

of the indoor units may be polluted by 

substances generated from the coating

and adhesives used for the interior finish

work and cause water splash and leakage. 

Содержание FDYQN71LBV1

Страница 1: ...onditioners MODELS Ceiling concealed duct type FDYQ N 71LBV1 FDYQ T N 100LBV1 FDYQ T 125LBV1 FDYQ T 140LCV1 FDYQ T 160LBV1 PLEASE READ THESE INSTRUCTIONS CAREFULLY BEFORE INSTALLATION KEEP THIS MANUAL...

Страница 2: ......

Страница 3: ...6 INDOOR UNIT INSTALLATION 7 REFRIGERANT PIPING WORK 7 DRAIN PIPING WORK 9 ELECTRICAL WIRING WORK 10 WIRING EXAMPLE 12 FIELD SETTINGS 14 TEST OPERATION 19 CHECKING PROCEDURE FOR ERROR RECORD 22 REGIS...

Страница 4: ...ak Toxic gas may be produced if the refrigerant gas leaks into the room and comes into contact with a source of fire such as a fan heater stove or cooker Before obtaining access to the terminals and e...

Страница 5: ...TIONS Be sure to read this manual before installing the indoor unit This unit is for indoor use only This unit is suitable for installation in a household commercial and light industrial environment D...

Страница 6: ...bration and noise can be transmitted into building Is the airflow within specification Poor performance or malfunction Is an air filter installed in the return air Blocked heat exchanger causing malfu...

Страница 7: ...r is introduced into the ceiling or the unit operates for 24 hours It is also important that a safety drain tray be used see Fig 11 PREPARATION BEFORE INSTALLATION To facilitate installation the indoo...

Страница 8: ...as shown in the diagrams Fig 6 4 Tighten the upper nut REFRIGERANT PIPING WORK ALL REFRIGERANT PIPING WORK MUST ONLY BE CARRIED OUT BY A QUALIFIED PERSON For refrigerant piping of outdoor units see th...

Страница 9: ...ch does not require flux Flux has an extremely harmful influence refrigerant piping systems For instance if chlorine based flux is used it will cause pipe corrosion particularly if the flux contains f...

Страница 10: ...piping with either the same diameter or with the diameter larger excluding the raised section than that of the connecting pipe PVC pipe nominal diameter 25mm outside diameter 32mm Keep the drain pipe...

Страница 11: ...local codes ie AS NZS 3000 A circuit breaker capable of shutting down power supply to the entire system must be installed Select and install the power supply wiring and transmission wiring in accorda...

Страница 12: ...t below the terminal block Do not connect the N line with the earth terminal Wiring between indoor and outdoor units Connect the transmission wire between the indoor and outdoor unit using terminals 1...

Страница 13: ...cribed wires are used carry out complete connections and secure the wires so that outside forces are not applied to the terminals CAUTION After connecting the wires be sure that no pressure is applied...

Страница 14: ...d o o r u n i t e x a m p l e N I s o l a t i o n s w i t c h F u s e N P o w e r s u p p l y N L N L M a i n p o w e r s u p p l y I s o l a t i o n s w i t c h F u s e N I s o l a t i o n s w i t c...

Страница 15: ...ormation in the option handbook Wired Remote Controller BRC1E62 1 Press and hold the Cancel button for 4 seconds or longer Service Settings menu is displayed 2 Select Field settings in the Service Set...

Страница 16: ...ory setting is the highest speed ie 15 so if you experience excessive airflow during post installation checks please follow the field setting instructions to set a lower airflow Please note that any c...

Страница 17: ...low Adjustment is successful do steps 3 to 4 7 02 should appear if not set the Automatic Airflow Adjustment again Note 1 If the indoor unit does not stop in the period of 10 minutes or 7 02 does not a...

Страница 18: ...17 Ducted Air Conditioners Installation Manual OTHER SETTINGS Applicable to all models...

Страница 19: ...ower Checking the connection Please stand by During above display backlight does not light by button operation When 1 indoor unit is controlled by 2 remote controllers Be sure to set sub remote contro...

Страница 20: ...n according to following procedure 1 Make sure to turn on the power supply more than 6 hours before operation start with front panel closed to protect compressor 2 Confirm that stop valves of both liq...

Страница 21: ...rvice Settings menu is displayed 11 Select Test Operation in the Service Settings menu and press Menu Enter button Basic screen returns and normal operation is conducted Note Test operation will autom...

Страница 22: ...ct the failure diagnosis referring to Malfunction code list in the installation manual of the indoor unit After the failure diagnosis finishes press and hold ON OFF button for 4 seconds or longer in t...

Страница 23: ...the Service Settings menu and press Menu Enter button The Error History menu screen is displayed 3 Select RC Error History in the Error History menu and press Menu Enter button Malfunction Error code...

Страница 24: ...nu and press Menu Enter button Maintenance Contact menu screen is displayed 3 Select Maintenance Contact and press Menu Enter button 4 Enter the telephone number Numeric varies by using Down Up button...

Страница 25: ...istor cables Socket location X18A X17A only for FDYQ71LB1 FDYQN100LBV1 models Fig 22 3 Remove 4 screws securing the electrical box to the fan deck compartment Fig 20 4 Untwist wire clamp securing the...

Страница 26: ...an motor wiring Fig 20 12 Secure the fan deck compartment with 4 M6 bolts bolt Fig 20 13 Pass the 2 thermistor cables through the rubber bush on the electric box and plug in the respective sockets X18...

Страница 27: ...26 Ducted Air Conditioners Installation Manual...

Страница 28: ...a Phone 1300 36 24 38 Dakin New Zealand 525 Great South Rd Penrose Auckland 6 www daikin com au DAIKIN INDUSTRIES LTD Head office Umeda Centre Bldg 2 4 12 Nakazaki Nishi Kita ku Osaka 530 8323 Japan T...

Отзывы: