The ILB8 & ILB10 inline blowers 

are only approved in updraft 

(hood) applications.

NOTE: 

The REMP must be sealed 

between the roof or wall and 

the underside of the flange with 

mastic to prevent leaks. For 

installation on a flat roof, or a 

roof with a pitch of less than 2:12, 

install the REMP on a curb as 

shown below. Position the curb 

on flat roofs so that the discharge 

(low) end points away from the 

prevailing wind.

RV

REMP

Dacor Preference

and Millennia Cooktops

AIR

3 1/4" x 10"

90° Elbow

3 1/4" x 10"

90° Elbow

3 1/4" x 10" to

Round

Transistion

45° Adjustable

Elbow

Air

Discharge

REMP Roof Installation

Side View

Roof Curb

REMP Flat Roof Installation

Sealant

Air

Discharge

Sealant

REMP

Round Duct

45° Adjustable

Elbow

Flange

REMP Sloped Roof Installation

25 1/2"

(648mm)

2"

(51mm)

19"

(483mm)

23 1/4"

(591mm)

6"

(152mm)

2"

(51mm)

REMP3 Sloped Roof Installation

33 1/2"

(851mm)

2"

(51mm)

26"

(660mm)

30 1/2"

(776mm)

6"

(152mm)

2"

(51mm)

REMP16 Roof Curb Dimensions

Electrical Connection

WARNINGS:

1.  Ensure that the power supply 

is disconnected before 

proceeding.

2.  Verify that the power supply 

matches the ratings found on 

the appliance data plate before 

proceeding.

3.  The complete appliance must 

be properly grounded at all 

times when electrical power is 

applied.

4.  Do not ground the appliance 

with the neutral (white) house 

supply wire. A separate 

ground wire must be utilized.

5.  If aluminum house supply 

wiring is used, splice the 

appliance copper wires to the 

aluminum house wiring with 

special connectors designed 

and agency-certified for this 

purpose. Follow the connector 

manufacturer’s recommended 

procedure carefully. Improper 

connection can result in a fire 

hazard.

6.   Failure to complete electrical 

connections properly may 

result in a damaged or non-

functional system. Follow the 

wiring diagrams carefully to 

ensure a proper installation. 

It is the owner’s responsibility to ensure that 

a qualified electrician performs the electrical 

connection of this appliance. The electrical 

installation, including minimum supply wire 

size, must comply with the latest revision of the 

National Electric Code ANSI/NFPA 70* and local 

codes and ordinances.

*A copy of this standard may be obtained from:

National Fire Protection Association

1 Batterymarch Park

Quincy, Massachusetts 02269-9101

NOTES: 

1.  Make all electrical connections 

between the vent and blowers, 

then connect power to the 

vent as per the wiring diagram 

shown.

2.  Use wire nuts and electrical 

tape to secure all wiring 

connections at the blowers.

Содержание ILB8

Страница 1: ...prior to operating this appliance TABLE OF STEPS Installation Planning Pages 2 3 Electrical Connection Pages 3 5 Installing the ILB Page 6 Installing the REMP Page 6 Verifying Proper Operation Page 6 Part No 65265 Rev D TESTED IN ACCORDANCE WITH THE LATEST EDITION OF ANSI UL507 STANDARD FOR ELECTRIC FANS AND CSA C22 2 NO 113 STANDARD FOR FANS AND VENTILATORS NOTES Contain helpful hints and tips to...

Страница 2: ...f the surface element WARNING TO REDUCE THE RISK OF INJURY TO PERSONS IN THE EVENT OF A RANGE TOP GREASE FIRE OBSERVE THE FOLLOWING a SMOTHER FLAMES with a close fitting lid cookie sheet or metal tray then turn off the burner BE CAREFUL TO PREVENT BURNS If the flames do not go out immediately EVACUATE AND CALL THE FIRE DEPARTMENT b NEVER PICK UP A FLAMING PAN You may be burned c DO NOT USE WATER i...

Страница 3: ...eter REMP3 19 483mm 5 13 16 148mm 25 1 2 648mm 8 203mm REMP16 26 660mm 9 9 16 243mm 33 1 2 851mm 10 254mm Model No Electrical Supply Requirements Maximum Duct Length Total Connected Load Blower Rating Approx Shipping Weight Finish REMP3 Refer to Ventilator Specifications Max 60 Equivalent Straight Feet 0 5kW 4A 620 CFM 35 lbs Galvanized may be painted REMP16 0 3kW 3A 980 CFM 55 lbs REMP Overall Di...

Страница 4: ... The complete appliance must be properly grounded at all times when electrical power is applied 4 Do not ground the appliance with the neutral white house supply wire A separate ground wire must be utilized 5 If aluminum house supply wiring is used splice the appliance copper wires to the aluminum house wiring with special connectors designed and agency certified for this purpose Follow the connec...

Страница 5: ...of RV with REMP and CABP3 N1 L1 N2 L2 N2 Gnd BLK WHT 120VAC 60Hz 15A Supply power from dedicated circuit breaker GRN WHT L2 BLK BLK WHT Gnd GRN Gnd GRN GRN WHT BLK RV REMP OR CABP3 Wiring of RV with REMP or CABP3 N1 L1 N2 L2 N2 Gnd BLK WHT 120VAC 60Hz 15A Supply power from dedicated circuit breaker GRN WHT L2 BLK BLK WHT Gnd GRN Gnd GRN GRN WHT BLK ERV PRV REMP Wiring of ERV PRV with REMP ...

Страница 6: ... Wiring of DACOR Remote Blower Hood with ILB and REMP L1 N1 Gnd L2 N2 Gnd L2 N2 Gnd GRN WHT 120VAC 60Hz 15A Supply power from dedicated circuit breaker BLK GRN WHT BLK GRN WHT BLK REMP HOOD Wiring of DACOR Hood with REMP L1 N1 Gnd L2 N2 Gnd L2 N2 Gnd GRN WHT BLK GRN WHT 120VAC 60Hz 15A Supply power from dedicated circuit breaker BLK GRN WHT BLK HOOD ILB GRN WHT BLK Wiring of DACOR Hood with ILB ...

Страница 7: ...tions on verifying the proper operation NOTES If the remote blower does not operate properly follow these troubleshooting steps 1 Verify that power is being supplied to the Ventilator and the remote blower 2 Check the electrical connections to ensure that the installation has been completed correctly 3 Repeat the above test 4 If the appliance still does not work contact an authorized DACOR service...

Страница 8: ...Web Site www dacor com For a Dealer Service 800 772 7778 Corporate Phone 800 793 0093 ...

Отзывы: