DXS-3610 Series Layer 3 Stackable 10GbE Managed Switch Hardware Installation Guide
13
Figure 3-9 Installed AC PSU Module
A second AC PSU module can be installed into the second PSU module slot labelled
PSU-2
. If the primary AC PSU
fails, the second AC PSU is used to provide AC power to the Switch. This takes place immediately and automatically.
When the AC PSU module is securely installed, plug one end of the AC power cord into the AC power socket on the
AC PSU module and the other end of the AC power cord into a properly grounded AC power source outlet. There is
no power switch/button on the Switch. The system will automatically power on and adjust its power settings to adapt to
any voltage supplied within the 100~240VAC range at 50~60Hz.
Installing DC PSU Modules
Switches in this series can also be shipped with two pre-installed DC PSU modules. This section can be referenced
when one or more DC PSU modules need to be replaced.
CAUTION:
Make sure that the DC power supply source is disconnected from the Switch and that the
Switch is not receiving any power. The power, fan, and other LED indicators must be off.
ATTENTION
:
Assurez-vous que la source d'alimentation CC est déconnectée du commutateur et que
celui-ci n’est pas alimenté. L'alimentation, le ventilateur et les autres voyants à LED doivent être
éteints.
To remove an existing DC PSU module, press the release clip to the side and gently pull the DC PSU module out of
the power supply module slot.