5. Installing Stand Alone Display Units
PNEG-1323
Integra Feed-Link
17
Installing Stand Alone Bin
Mounted Display Units
1. Load cell wires
a. Slide all load cell cables through
grommet cap.
b. Run load cell cables into multi-hole
grommet by sliding cables through slit on
side of grommet.
c. Run cables through hole in display box,
giving some extra cable length for
easier installation.
d. To make load cell connections, remove
terminals strips. Insert wires into correct
terminals and tighten lugs.
e. Gently pull out any excess length of
cable out through the grommet.
f. Wedge grommet into hole.
g. Tighten grommet nut cap.
NOTE: If only three (3) or four (4) holes are used
in the grommet, you need to seal the open
holes using the plugs supplied to make it
water tight.
Figure 5D A) Load cell wire in multi-hole grommet.
B) Grommet wedged into connector.
Figure 5E A) Load cell wires going into display box.
B) Cap tightened onto load cell wires.
Figure 5F Load Cell Connections to Display Box
Always make sure all power is
disconnected and locked out
while display unit cover is OFF.
A
B
Multi-hole grommet
Plug
Multi-hole grommet
Connector
B
Load cell wires
Power wires
(grommet not included)
Water
meter wires
Grommet cap
Daisy chain “IN” wires
Daisy chain
“OUT” wires
or RF wires
A
Terminal strips
Load cell 3
ground (Black)
Load cell 1 and 2
ground (Black)
Load cell 3
power (Red)
Load cell 1 and
2 power (Red)
Load cell 1 signal (White)
Load cell 2
signal (White)